Page 4
Copyright This document and parts thereof must not be reproduced or copied without written permission from ABB, and the contents thereof must not be imparted to a third party, nor used for any unauthorized purpose. The software and hardware described in this document is furnished under a license and may be used or disclosed only in accordance with the terms of such license.
Page 5
This document has been carefully checked by ABB but deviations cannot be completely ruled out. In case any errors are detected, the reader is kindly requested to notify the manufacturer.
Page 6
(EMC Directive 2004/108/EC) and concerning electrical equipment for use within specified voltage limits (Low-voltage directive 2006/95/EC). This conformity is the result of tests conducted by ABB in accordance with the product standard EN 60255-26 for the EMC directive, and with the product standards EN 60255-1 and EN 60255-27 for the low voltage directive.
Checking the IED operation...............46 IED start-up sequence...............47 Setting up communication between PCM600 and the IED.....47 Writing an application configuration to the IED........52 Checking CT circuits................53 Checking VT circuits................54 Using the RTXP test switch..............54 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 8
Section 9 Establishing connection and verifying the IEEE C37.118/1344 communication..........73 Overview....................73 Setting the PMU station communication (PMU Report)......73 Setting the PMU station communication (PMU configuration)....74 Setting the TCP/UDP client communication........... 75 Verifying the communication..............78 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 9
Identifying the function to test in the technical reference manual ..107 Differential protection................107 Transformer differential protection T2WPDIF andT3WPDIF(87T).. 107 Verifying the settings..............107 Completing the test..............108 High impedance differential protection HZPDIF (87)....... 108 Verifying the settings..............109 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 10
ZMFCPDIS (21)..... 137 Measuring the operating limit of set values........ 140 Measuring the operating time of distance protection zones..141 Completing the test..............141 Power swing detection ZMRPSB (68)..........142 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 11
Instantaneous phase overcurrent protection 3-phase output PHPIOC (50)..................177 Measuring the trip limit of set values.......... 177 Completing the test..............178 Directional phase overcurrent protection, four steps OC4PTOC (51_67).....................178 Verifying the settings..............178 Completing the test..............180 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 12
Verifying the settings..............197 Completing the test..............199 Directional overpower protection GOPPDOP (32)......199 Verifying the settings..............199 Completing the test..............200 Broken conductor check BRCPTOC (46)........200 Measuring the trip and time limit of set values......200 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 13
Measuring the trip limit of set values.......... 222 Completing the test..............222 Frequency protection................223 Underfrequency protection SAPTUF (81)........223 Verifying the settings..............223 Completing the test..............224 Overfrequency protection SAPTOF (81)......... 224 Verifying the settings..............224 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 14
Voltage control TR1ATCC, TR8ATCC, TCMYLTC, TCLYLTC..247 Secondary test................249 Check the activation of the voltage control operation....249 Check the normal voltage regulation function......250 Check the undervoltage block function........251 Check the upper and lower busbar voltage limit......251 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 15
Testing the current reversal logic..........267 Testing the weak-end infeed logic..........268 Completing the test..............270 Logic..................... 270 Tripping logic, common 3-phase output SMPPTRC (94)....270 3 phase operating mode.............270 1p/3p operating mode..............271 1p/2p/3p operating mode............271 Circuit breaker lockout..............272 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 16
Binary signal transfer...............283 Basic IED functions................284 Parameter setting group handling SETGRPS......... 284 Verifying the settings..............285 Completing the test..............285 Exit test mode..................285 Section 12 Primary injection testing............ 287 Transformer Voltage Control ATCC............287 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 17
General IED status..............303 Fault tracing..................304 Internal fault indications..............304 Using front-connected PC............... 305 Diagnosing the IED status via the LHMI hint menu......307 Repair instruction..................309 Repair support..................310 Maintenance..................310 Section 16 Glossary................311 Transformer protection RET670 2.2 ANSI Commissioning manual...
The commissioning personnel must have a basic knowledge of handling electronic equipment. The commissioning and maintenance personnel must be well experienced in using protection equipment, test equipment, protection functions and the configured functional logics in the IED. Transformer protection RET670 2.2 ANSI Commissioning manual...
The installation manual contains instructions on how to install the IED. The manual provides procedures for mechanical and electrical installation. The chapters are organized in the chronological order in which the IED should be installed. Transformer protection RET670 2.2 ANSI Commissioning manual...
The guideline can be used as a technical reference during the engineering phase, installation and commissioning phase, and during normal service. 1.3.2 Document revision history Document revision/date History –/May 2017 First release Transformer protection RET670 2.2 ANSI Commissioning manual...
The warning icon indicates the presence of a hazard which could result in personal injury. The caution hot surface icon indicates important information or warning about the temperature of product surfaces. Transformer protection RET670 2.2 ANSI Commissioning manual...
For example, to save the changes in non-volatile memory, select Yes and press • Parameter names are shown in italics. For example, the function can be enabled and disabled with the Operation setting. • Each function block symbol shows the available input/output signal. Transformer protection RET670 2.2 ANSI Commissioning manual...
National and local electrical safety regulations must always be followed. Working in a high voltage environment requires serious approach to avoid human injuries and damage to equipment. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 36
Never remove any screw from a powered IED or from a IED connected to powered circuitry. Potentially lethal voltages and currents are present. Take adequate measures to protect the eyes. Never look into the laser beam. Transformer protection RET670 2.2 ANSI Commissioning manual...
IED circuitry. Take care to avoid electrical shock during installation and commissioning. Changing the active setting group will inevitably change the IEDs operation. Be careful and check regulations before making the change. Transformer protection RET670 2.2 ANSI Commissioning manual...
Section 2 1MRK 504 165-UUS - Safety information Note signs Observe the maximum allowed continuous current for the different current transformer inputs of the IED. See technical data. Transformer protection RET670 2.2 ANSI Commissioning manual...
Directional phase overcurrent protection, four steps 51_67 EFPIOC Instantaneous residual overcurrent protection EF4PTOC Directional residual overcurrent protection, four steps NS4PTOC 46I2 Four step directional negative phase sequence overcurrent protection Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 41
Frequency protection SAPTUF Underfrequency protection SAPTOF Overfrequency protection SAPFRC Rate-of-change of frequency protection Multipurpose protection CVGAPC General current and voltage protection General calculation SMAIHPAC Multipurpose filter 1) 67 requires voltage 2) 67N requires voltage Transformer protection RET670 2.2 ANSI Commissioning manual...
I103USRCMD Function commands user defined for IEC 60870-5-103 Secondary system supervision CCSSPVC Current circuit supervision FUFSPVC Fuse failure supervision VDSPVC Fuse failure supervision based on voltage difference Logic Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 43
Integer to Boolean 16 conversion ITBGAPC Integer to Boolean 16 conversion with Logic Node representation TEIGAPC Elapsed time integrator with limit transgression and overflow supervision INTCOMP Comparator for integer inputs REALCOMP Comparator for real inputs Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 44
ABC_BC BH_CONN BH_LINE_A BH_LINE_B DB_BUS_A DB_BUS_B DB_LINE ABC_LINE AB_TRAFO SCSWI Switch controller SXSWI Circuit switch QCRSV Apparatus control RESIN1 RESIN2 POS_EVAL Evaluation of position indication QCBAY Bay control Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 45
INVALIDQT INVERTERQT ORQT PULSETIMERQT RSMEMORYQT SRMEMORYQT TIMERSETQT XORQT Table 6: Total number of instances for extended logic package Extended configurable logic block Total number of instances GATE PULSETIMER RSMEMORY SLGAPC SRMEMORY TIMERSET VSGAPC Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 46
IED status for IEC 60870-5-103 I103SUPERV Supervison status for IEC 60870-5-103 I103USRDEF Status for user defined signals for IEC 60870-5-103 L4UFCNT Event counter with limit supervision TEILGAPC Running hour meter Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
GOOSE function block to receive a measurand value GOOSESPRCV GOOSE function block to receive a single point value GOOSEVCTRRCV Horizontal communication via GOOSE for VCTR GOOSEVCTRCONF GOOSE VCTR configuration for send and receive Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 48
BinSigRec1_22M BinSigTran1_12M BinSigTran1_22M LDCMTRN Transmission of analog data from LDCM LDCMTRN_2M Transmission of analog data from LDCM, 2Mbit LDCMRecBinStat1 Receive binary status from remote LDCM 6/3/3 LDCMRecBinStat2 LDCMRecBinStat3 Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
SYNCHCMPPS, SYNCHLON, SYNCHPPH, SYNCHPPS, SNTP, SYNCHSPA Precision time protocol TIMEZONE Time synchronization IRIG-B Time synchronization SETGRPS Number of setting groups ACTVGRP Parameter setting groups TESTMODE Test mode functionality Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 50
Parameter setting function for HMI in PCM600 FNKEYMD1– FNKEYMD5 LEDGEN General LED indication part for LHMI OPENCLOSE_LED LHMI LEDs for open and close keys GRP1_LED1– Basic part for CP HW LED indication module GRP1_LED15 GRP2_LED1– GRP2_LED15 GRP3_LED1– GRP3_LED15 Transformer protection RET670 2.2 ANSI Commissioning manual...
Before starting up commissioning at site, check that the following items are available. • Single line diagram • Protection block diagram • Circuit diagram • Setting list and configuration • RJ-45 Ethernet cable (CAT 5) Transformer protection RET670 2.2 ANSI Commissioning manual...
Check also the self-supervision function in Main menu/Diagnostics/IED status/ General menu in local HMI to verify that the IED operates properly. Transformer protection RET670 2.2 ANSI Commissioning manual...
The communication between the IED and PCM600 is independent of the communication protocol used within the substation or to the NCC. The communication media is always Ethernet and the used transport layer is TCP/IP. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 54
An ethernet cable (max 2 m length) with RJ-45 connectors is needed to connect two physical Ethernet interfaces together without a hub, router, bridge or switch in between. Select Search programs and files in the Start menu in Windows. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 55
Section 4 1MRK 504 165-UUS - Starting up IEC13000057-1-en.vsd IEC13000057 V1 EN Figure 3: Select: Search programs and files Type View network connections and click on the View network connections icon. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 56
Right-click and select Properties. IEC13000059-1-en.vsd IEC13000059 V1 EN Figure 5: Right-click Local Area Connection and select Properties Select the TCP/IPv4 protocol from the list of configured components using this connection and click Properties. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 57
IP address is not set to be obtained automatically by the IED, see Figure 7. The IP address must be different from the IP address chosen for the IED. Transformer protection RET670 2.2 ANSI Commissioning manual...
Writing an application configuration to the IED When writing a configuration to the IED with PCM600, the IED is automatically set in configuration mode. When the IED is set in configuration mode, all functions are blocked. Transformer protection RET670 2.2 ANSI Commissioning manual...
While the CT primary is energized, the secondary circuit shall never be open circuited because extremely dangerous high voltages may arise. Both the primary and the secondary sides must be disconnected from the line and the IED when plotting the excitation characteristics. Transformer protection RET670 2.2 ANSI Commissioning manual...
CT secondary circuit and opens the VT secondary circuits making the IED available for secondary injection. When pulled out, the test handle is mechanically stopped in half withdrawn position. In this position, the current and voltage enter the protection, but the alarm and trip circuits are Transformer protection RET670 2.2 ANSI Commissioning manual...
4.10.1 Binary input circuits Preferably, disconnect the binary input connector from the binary input cards. Check all connected signals so that both input level and polarity are in accordance with the IED specifications. Transformer protection RET670 2.2 ANSI Commissioning manual...
An IED equipped with optical connections has an minimum space requirement of 180 mm (7.2 inches) for plastic fiber cables and 275 mm (10.9 inches) for glass fiber cables. Check the allowed minimum bending radius from the optical cable manufacturer. Transformer protection RET670 2.2 ANSI Commissioning manual...
(including setting the Local/Remote switch to the desired position) for at least one hour after the last commissioning action performed on the IED. After that time has elapsed, it will be safe to turn the IED off, no data will be lost. Transformer protection RET670 2.2 ANSI Commissioning manual...
Take the rated permissive overload values for the current inputs into consideration. Supervision of input/output modules I/O modules configured with PCM600 (BIM, BOM or IOM) are supervised. I/O modules that are not configured are not supervised. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 65
Each logical I/O module has an error flag that indicates signal or module failure. The error flag is also set when the physical I/O module of the correct type is not detected in the connected slot. Transformer protection RET670 2.2 ANSI Commissioning manual...
The SPA/IEC port is located on the rear side of the IED. Two types of interfaces can be used: • plastic fibres with connector type HFBR • glass fibres with connector type ST When using the IEC protocol, the rear SPA/IEC port must be set for IEC use. Transformer protection RET670 2.2 ANSI Commissioning manual...
SMS/SCS system are as expected. 6.2.2 Verifying IEC communication To verify that the IEC communication with the IEC master system is working, there are some different methods. Choose one of the following. Procedure Transformer protection RET670 2.2 ANSI Commissioning manual...
0.16 dB/m plastic: 620 nm - 1mm 4 dB Margins for installation, aging, and so on 5 dB 1 dB Losses in connection box, two contacts (0.5 dB/contact) 1 dB Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 70
Distance 1 km Distance 25 m Glass Plastic Losses in connection box, two contacts (1 dB/contact) 2 dB Margin for 2 repair splices (0.5 dB/splice) 1 dB Maximum total attenuation 11 dB 7 dB Transformer protection RET670 2.2 ANSI Commissioning manual...
Example of LON communication structure for a substation automation system An optical network can be used within the substation automation system. This enables communication with the IEDs through the LON bus from the operator’s workplace, from Transformer protection RET670 2.2 ANSI Commissioning manual...
MicroSCADA. When using MicroSCADA Monitor Pro instead of the Classic Monitor, SA LIB is used together with 670 series Object Type files. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 73
Parameter Range Default Unit Parameter description DomainID Domain identification number SubnNetAddr* 0 - 255 Subnet address Step: 1 NodeAddr* 0 - 127 Node address Step: 1 *Can be viewed on the local HMI Transformer protection RET670 2.2 ANSI Commissioning manual...
0.3 dB/m plastic: 620 nm - 1mm 3 dB Margins for installation, aging, and so on 5 dB 2 dB Losses in connection box, two contacts (0.75 dB/contact) 1.5 dB Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 75
Establishing connection and verifying the LON communication Distance 1 km Distance10 m Glass Plastic Losses in connection box, two contacts (1dB/contact) 2 dB Margin for repair splices (0.5 dB/splice) 0.5 dB Maximum total attenuation 11 dB 7 dB Transformer protection RET670 2.2 ANSI Commissioning manual...
Activate IEC 61850-8-1 (substation bus) communication. Navigate to: Main menu/Configuration/Communication/Station communication/IEC61850–8–1/IEC61850–8–1:1 Enable operation for Access Point 1 and 3 in the Ethernet configuration tool (ECT) in PCM600. Enable redundant communication for Acess point 1 using ECT. Transformer protection RET670 2.2 ANSI Commissioning manual...
Verify that either signal status (depending on which connection that was removed) is shown as Error and the that other signal is shown as Ok. Be sure to re-connect the removed connection after completed verification. Transformer protection RET670 2.2 ANSI Commissioning manual...
1.1. Make sure that the operation of at least one PMU instance (e.g. PMU1) is Enabled. 1.2. Enable sending the frequency data by setting the parameter SendFreqInfo to Enabled. Check the operation of the required phasor channels (PHASORREPORT) by navigating to: Main menu/Configuration/Communication/Station communication/phasor measurement/PMU Report/PHASORREPORT:x. Transformer protection RET670 2.2 ANSI Commissioning manual...
LAN IP address of the PC is used, where the PDC client tool is installed. 3.3. The default parameter settings can be used for the rest of parameters for the first UDP group. Transformer protection RET670 2.2 ANSI Commissioning manual...
The following steps explain how to set the PMU Connection Tester parameters in order to establish an IEEE C37.118 connection with the PMU: Set the IP stack on PMU Connection Tester to IPv4. Note that the default IP stack on PMU Connection Tester tool is IPv6. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 82
1.2. Force the IP stack to IPv4 by setting the parameter ForceIPv4 to True. Set the Connection Parameters on PMU Connection Tester for TCP communication according to the PMU configuration. IEC140000135-1-en.vsd IEC140000135 V1 EN Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 83
3.2. Click the Configure Alternate Command Channel to configure the TCP channel. A new window will pop up. A TCP channel needs to be configured in order to control the UDP data communicatiuon and transfer the header, configuration and command frames. Transformer protection RET670 2.2 ANSI Commissioning manual...
Alternatively, the PMU Connection Tester tool can be used to verify the IEEE C37.118/1344 communication. The section Setting the TCP/UDP client communication explains how to Transformer protection RET670 2.2 ANSI Commissioning manual...
Now it should be possible to see the streaming synchrophasor data. In the Graph tab, observe the Frequency, data Reporting Rate, Phasor names, and Phase angles of the reported synchrophasors. Observe the real-time frame details of the Data Frame in the bottom of the window. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 86
Open the drop-down menu in the Command field. There is a list of commands that can be sent from the client (PMU Connection Tester) to the PMU. Try different commands and make sure that the PMU is receiving and responding to them. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 87
If the HeaderFrame is not included, ask the PMU to send the header frame via the Send Header Frame command (Previous stage). Open each message type and observe the content of each message. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 88
It is also possible to capture the IEEE C37.118 synchrophasor data in an Excel file. This is done by navigating to File/Capture/Start Stream Debug Capture... The tool will ask to Set Stream Debug Capture File Name and path to save the capture file. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 89
IEC140000142 V1 EN Figure 14: Start capturing the IEEE C37.118 synchrophasor data • The synchrophasor data capturing process can be stopped at any point of time by navigating to File/Capture/Stop Stream Debug Capture... Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 90
Phasor names on top of each column (See figure 16), the capture process should start before connecting the PMU Connection Tester to the PMU, i.e. first start the capturing and then click Connect. Transformer protection RET670 2.2 ANSI Commissioning manual...
Setting the PMU station communication (PMU Report), Setting the PMU station communication (PMU configuration) Setting the TCP/UDP client communication) and making sure that the Ethernet communication is set up, click Connect on the PMU Connection Tester tool. Transformer protection RET670 2.2 ANSI Commissioning manual...
WAN/LAN access point, it is important to know what is the optical budget available. The graph in Figure shows the dynamic range available for a PMU – PDC configuration using typical OEMs. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 93
Losses in the connectors and splices are typically 0.3dB/connection. The user must reserve 3dB spare for the uncertainty of the measurements. Transformer protection RET670 2.2 ANSI Commissioning manual...
The voltages and currents from the test equipment must be obtained from the same source and they must have minimal harmonic content. If the test equipment cannot indicate the phase angle, a separate phase-angle measuring instrument is necessary. Transformer protection RET670 2.2 ANSI Commissioning manual...
This means connecting the test equipment according to a specific and designated IED terminal diagram. Put the IED into the test mode to facilitate the test of individual functions and prevent unwanted operation caused by other functions. The busbar differential protection is not Transformer protection RET670 2.2 ANSI Commissioning manual...
In this way, it is possible to test slower back-up measuring functions without the interference from faster measuring functions. The test switch should then be connected to the IED.Test mode is indicated when the yellow PickupLED flashes. Transformer protection RET670 2.2 ANSI Commissioning manual...
The test switch and its associated test plug handles are a part of the COMBITEST or FT system of ABB, which provides secure and convenient testing of the IED. When using the COMBITEST, preparations for testing are automatically carried out in the proper sequence, that is, for example, blocking of tripping circuits, short circuiting of CTs, opening of voltage circuits, making IED terminals available for secondary injection.
TRIP A TRIP B TRIP C IEC 61850 ANSI09000652-1-en.vsd ANSI09000652 V1 EN Figure 19: Connection example of the test equipment to the IED when test equipment is connected to the transformer input module Transformer protection RET670 2.2 ANSI Commissioning manual...
Set parameter Blocked for the selected function to No. 10.6 Verifying analog primary and secondary measurement Verify that the connections are correct and that measuring and scaling is done correctly. This is done by injecting current and voltage to the IED. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 101
If some setting deviates, check the analog input settings under Main menu/Configuration/Analog modules If the IEC/UCA 61850-9-2LE communication is interrupted during current injection, the report tool in PCM600 will display the current that was injected before the interruption. Transformer protection RET670 2.2 ANSI Commissioning manual...
Use the disturbance handling tool in PCM600 to evaluate that the protection function has received the correct data and responded correctly (signaling and timing). • Use the event viewer tool in PCM600 to check that only expected events have occurred. Transformer protection RET670 2.2 ANSI Commissioning manual...
LHMI/PCM600 menus that relate to forcing will not have any effect on the input/output status due to safety reasons. 10.8.2.1 Enable forcing by using LHMI Enable IED TESTMODE by setting IEDTestMode to On under Main menu/ Test/IED test mode/TESTMODE:1. Transformer protection RET670 2.2 ANSI Commissioning manual...
Edit the input/output value directly to select the desired logical level, by doing following: Select the value line of the desired signal, see figure 21. Press the Enter key to edit the value. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 105
When navigating away from a LHMI forcing menu for an I/O board, the user is prompted to either leave the signals forced, or to revert all of them back to the unforced state. IEC15000022 V1 EN Transformer protection RET670 2.2 ANSI Commissioning manual...
IED, potentially changing inputs and outputs on multiple I/O boards at the same time. It is also possible to abort this operation (described in step 6 below) and to undo all forcing. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 107
Click Start editing signal value for forcing on the tool bar. IEC15000024 V1 EN The Signal Monitoring menu changes and indicates the forcing values that can be edited. IEC15000025 V1 EN Select and edit the values. Click Acknowledge and send. Transformer protection RET670 2.2 ANSI Commissioning manual...
This immediately undoes all forcing, regardless of how it was accomplished and disabled all the way to force signals. 10.8.4.2 Undo forcing by using LHMI • If the IED test mode was enabled to using the LHMI: Transformer protection RET670 2.2 ANSI Commissioning manual...
This may change both binary input values and output relay states and will undo any forcing done by using the LHMI. If the IED is left in test mode, then it is still possible to perform new forcing operations, both from LHMI and from PCM600 Transformer protection RET670 2.2 ANSI Commissioning manual...
The Manual Trig can be started in two ways: From the local HMI under Main menu/Disturbance records. 1.1. Enter on the row at the bottom of the HMI called Manual trig. Transformer protection RET670 2.2 ANSI Commissioning manual...
PCM600 as follows: on the local HMI under Main menu/Events, or in more details via the Event Viewer in PCM600. The internal FIFO register of all events will appear when the event viewer is launched. Transformer protection RET670 2.2 ANSI Commissioning manual...
Connect the test set for injection of three-phase currents to the current terminals of the IED, which are connected to the CTs on the HV side of the power transformer. Increase the current in phase A until the protection function operates and note the operating current. Transformer protection RET670 2.2 ANSI Commissioning manual...
Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. 11.3.2 High impedance differential protection HZPDIF (87) Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. 11.3.4 Additional security logic for differential protection LDRGFC (11) 11.3.4.1 Verifying the settings Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 117
12. Reduce the injected voltage stepwise to 90 % of the trip level, and check the time delay. 13. Repeat points 9 – 12 for phases B-C and C-A. Zero sequence overcurrent criteria Procedure Transformer protection RET670 2.2 ANSI Commissioning manual...
Restore connections and settings to their original values, if they were changed for testing purposes. 11.4 Impedance protection 11.4.1 Distance protection zones, quadrilateral characteristic ZMQPDIS (21) Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 119
The solid line and all test points except 13 are valid for this case. When the load current compensation is inactive, the dotted lines and test point 13 are valid. Test points 5, 6, and 7 are not valid for this measurement. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 120
ArgLd = angle for the maximal load 0.85 x RFPP x tan (ArgRLd) transfer 0.85 x RFPP RLdFw x tan (ArgLd) RLdFw RLdFw –0.2143 x RFPP/2 Exact: 0.8 x RFPP/2 (ArgDir=20°) 0.8 x RFPP/2 Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 121
80% of RLdFwd alt. 80% of RFPG RFPG (Load encroachment) ANSI05000369-2-en.vsd ANSI05000369 V2 EN Figure 24: Distance protection characteristic with test points for phase-to-ground measurements Table is used in conjunction with figure 24. Transformer protection RET670 2.2 ANSI Commissioning manual...
Exact: 0.8 x (2X1set + X0set)/(3 x tan(AgNegDir=30°) 0.5 x (2 x X1 + X0 0.5 x (2 x R1 + R0 Only used when RLdFw > RFPE RFPE 11.4.1.1 Measuring the operating limit of set values Procedure: Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
To verify the settings the operating points according to figures should be tested. See also tables for information. loop ArgNegRes loop 50% of RLdFwd RFltFwdPG ANSI09000734-2-en.vsd ANSI09000734 V2 EN Figure 25: Operating characteristic for phase selection function, forward direction single-phase faults Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 125
0,5·RLdFwd Table is used together with figure 25. phase LdAngle ArgNegRes 60° phase ArgDir 50% RLdFwd 0.5·RFltFwdPP ANSI09000735-1-en.vsd ANSI09000735 V1 EN Figure 26: Operating characteristic for phase selection function, forward direction phase-to-phase faults Transformer protection RET670 2.2 ANSI Commissioning manual...
HMI under Main menu/Test/Function status/Impedance Protection/PhaseSelection(PDIS, 21)/FDPSPDIS:x. Repeat steps to find the operate values for the remaining test points according to figure and table 20. Transformer protection RET670 2.2 ANSI Commissioning manual...
To verify the mho characteristic, at least two points should be tested. In the following, three test points are proposed. The mho characteristic always goes through the origin, which automatically gives a fourth point for the characteristic. Transformer protection RET670 2.2 ANSI Commissioning manual...
TRIP, TRPP and TR_x shall be activated. 11.4.3.2 Phase-to-ground faults For simplicity, the same test points as for phase-to-phase faults are proposed, but considering new impedance values. Transformer protection RET670 2.2 ANSI Commissioning manual...
TRIP, TRPG and TR_x shall be activated. 11.4.4 Faulty phase identification with load encroachment FMPSPDIS (21) There is no specific test routine for this function. The function is tested in conjunction with other impedance (mho) functions. Transformer protection RET670 2.2 ANSI Commissioning manual...
The solid line and all test points except 13 are valid for this case. Test points 5, 6, and 7 are not valid for this measurement. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 131
80% of RLdFwd alt. 80% of RFPG RFPG (Load encroachment) ANSI05000369-2-en.vsd ANSI05000369 V2 EN Figure 30: Distance protection characteristic with test points for phase-to-ground measurements Table is used in conjunction with figure 30. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 132
0.5 x RFPP Table 25: Test points for phase-to-earth L3-G (Ohm/Loop) Test point Reach Value Comments (2 x X1 (2 x X1 + X0 2 x R1 + R0 Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
1 according to test point 1 in figure and table 24. Compare the result of the measurement with the set value. Repeat steps to find the operating value for test points 2, 3 in table24. Transformer protection RET670 2.2 ANSI Commissioning manual...
Measure operating characteristics during constant current conditions. Keep the measured current as close as possible to the rated value of its associated input transformer, or lower. But ensure that it is higher than 30% of the rated current. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 135
To verify the settings the operating points according to figures should be tested. See also tables for information. loop ArgNegRes loop 50% of RLdFwd RFltFwdPG ANSI09000734-2-en.vsd ANSI09000734 V2 EN Figure 31: Operating characteristic for phase selection function, forward direction single-phase faults Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 136
Test point Value Comments [X1+XN] XN=(X RLdFwd 0.85·[X1+XN] R≈0.491·(X1+XN)+RFFwPE 0.85·[X1+XN]·1/tan(60°)+RFFwPE 0.85·[X1+XN] -0.85·[X1+XN]· tan (AngNegRes-90°) RFltFwdPG·tan (LdAngle) RFltFwdPG -0,5·RLdFwd·tan (ArgDir) 0,5·RLdFwd The table showing test points for phase-to-ground loops is used together with figure 31. Transformer protection RET670 2.2 ANSI Commissioning manual...
2 and 5 can be replaced by test point 7. Repeat steps to find the operate value for the phase-to-phase fault in A - C according to figure and table 27. Transformer protection RET670 2.2 ANSI Commissioning manual...
The solid line and all test points except 13 are valid for this case. When the load current compensation is inactive, the dotted lines and test point 13 are valid. Test points 5, 6, and 7 are not valid for this measurement. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 139
LdAngle = angle for the maximal load 0.85 x RFPPZx x tan (LdAngle) transfer 0.85 x RFPPZx RLdFwd x tan (LdAngle) RLdFwd RLdFw –0.2143 x RFPPZx/2 Exact: 0.8 x RFPPZx/2 (ArgDir=20°) 0.8 x RFPPZx/2 Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 140
80% of RLdFwd alt. 80% of RFPG RFPG (Load encroachment) ANSI05000369-2-en.vsd ANSI05000369 V2 EN Figure 34: Distance protection characteristic with test points for phase-to-ground measurements Table is used in conjunction with figure 34. Transformer protection RET670 2.2 ANSI Commissioning manual...
+ X0 Exact: 0.8 x (2X1set + X0set)/(3 x tan(AgNegDir=30°) 0.5 x (2 x X1 + X0 0.5 x (2 x R1 + R0 RFPG 11.4.7.1 Measuring the operating limit of set values Procedure: Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
The solid line and all test points except 13 are valid for this case. When the load current compensation is inactive, the dotted lines and test point 13 are valid. Test points 5, 6, and 7 are not valid for this measurement. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 144
0.85 x RFPPZx x tan (LdAngle) transfer 0.85 x RFPPZx RLdFwd x tan (LdAngle) RLdFwd RLdFwd x tan (LdAngle) –0.2143 x RFPPZx/2 Exact: 0.8 x RFPPZx/2 (ArgDir=20°) 0.8 x RFPPZx/2 Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 145
80% of RLdFwd alt. 80% of RFPG RFPG (Load encroachment) ANSI05000369-2-en.vsd ANSI05000369 V2 EN Figure 36: Distance protection characteristic with test points for phase-to-ground measurements Table is used in conjunction with figure 36. Transformer protection RET670 2.2 ANSI Commissioning manual...
+ X0 Exact: 0.8 x (2X1 + X0 )/(3 x tan(AgNegDir=30°) 0.5 x (2 x X1 + X0 0.5 x (2 x R1 + R0 11.4.8.1 Measuring the operating limit of set values Procedure: Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
ZMRPSB (68). The proposed test points for validation of the settings are numbered according to figure Test of the interactions or combinations that are not configured are not considered in this instruction. Transformer protection RET670 2.2 ANSI Commissioning manual...
PHG_FLT on the FDPSPDIS (21) or FRPSPDIS (21) function. • The input BLK_SS, block inhibit of the pickup output for subsequent residual current detection is connected to FALSE. Transformer protection RET670 2.2 ANSI Commissioning manual...
Prepare the IED for verification of settings as outlined in section "Requirements" section "Preparing for test" in this chapter. Most readily available test equipment does not permit simulation of power-swing conditions and the simultaneous occurrence of different faults with controlled fault Transformer protection RET670 2.2 ANSI Commissioning manual...
Additionally connect the IED according to the test instructions for the four step residual overcurrent protection function EF4PTOC (51N/67N), if the Power swing logic (PSLPSCH) is configured in a way that is controlled by this protection. Procedure Transformer protection RET670 2.2 ANSI Commissioning manual...
1 normal otrip time. Also, observe the BLKZMOR functional output signal, which must appear for a short time. Be sure to establish the original configuration of the IED and the original settings of all setting parameters. Transformer protection RET670 2.2 ANSI Commissioning manual...
This is done with a speed so that the final impedance is reached after 1 second. As the injected voltage is lower than 0.92 VBase the PICKUP signal should be activated. In addition to this the signal ZONE1 should be activated. Set N1Limit to 1 and repeat step 4. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 155
Now the signals TRIP2 and TRIP should be activated. Zone 1 Zone 2 X’ Pole slip impedance movement Zone 2 TripAngle Zone 1 WarnAngle ANSI07000099_2_en.vsd ANSI07000099 V2 EN Figure 38: Setting of the pole slip protection PSPPPAM (78) Transformer protection RET670 2.2 ANSI Commissioning manual...
1, which normally includes the generator and its step-up power transformer. If the center of oscillation is found to be further out in the power system, in zone 2, more than one pole- Transformer protection RET670 2.2 ANSI Commissioning manual...
RE (RE = Receiving End) • the intersection between the line segment SE-RE and the X-line, which is defined through the setting ReachZ1 • the point SE (SE = Sending End) Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 158
SE and RE. 2 5 8367 20918 × × Base (Equation 3) EQUATION14043 V1 EN Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 160
Symmetric three-phase voltage at 50 Hz. The magnitude depends on the point of the characteristic that needs to be verified. The following three main points of the line segment SE-RE need to be checked: Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 161
For the test as motor the frequency current may have 50.5 Hz in the quadrant 1 and 2 of the R-X plane and 49.5 Hz in the quadrant 3 and 4. Transformer protection RET670 2.2 ANSI Commissioning manual...
arctan arctan 82. . 14° ∠ = = ForwardR 8 19 (Equation 18) EQUATION14058 V1 EN frequency of V = 50 Hz Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 163
arctan arctan 82. . 14° ∠ = = ForwardR 8 19 (Equation 22) EQUATION14058 V1 EN frequency of V = 50 Hz =0 A Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 164
Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 0 9 11931 77 81 × × × × t FwdZ 13 8 VT p (Equation 27) EQUATION14063 V1 EN Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 165
(the phase angle is related to phase L1): VT s 0 9 11931 77 81 × × × × t FwdZ 13 8 VT p (Equation 31) EQUATION14063 V1 EN Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 166
× 9000 (Equation 36) EQUATION14062 V1 EN ∠I = 180º frequency of I = 49.5 Hz Expected result: start of the protection function and trip in zone 2, when trip conditions are fulfilled. Transformer protection RET670 2.2 ANSI Commissioning manual...
ROTORANG is close to 3.14 rad. For this particular injection the service values are: • VOLTAGE = 1.58 kV • CURRENT = 20918 A • R = 1.08% • X = 7.85% • ROTORANG = -3.04 rad Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 168
(Equation 44) EQUATION14058 V1 EN frequency of V = 50 Hz 10459 1 162 × × 9000 (Equation 45) EQUATION14059 V1 EN ∠I = 0º frequency of I = 50 Hz Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 169
= 50 Hz • Check that the service values (VOLTAGE, CURRENT, R(%), X(%)) are according to the injected quantities and that ROTORANG is close to 3.14 rad. For this particular injection the service values are: Transformer protection RET670 2.2 ANSI Commissioning manual...
ReverseR 0.29 (Equation 58) EQUATION14068 V1 EN frequency of V = 50 Hz 10459 1 162 × × 9000 (Equation 59) EQUATION14059 V1 EN ∠I = 0º frequency of I = 50 Hz Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 172
EQUATION14068 V1 EN frequency of V = 50 Hz = 0 A = 0 A • State 2: main test step. Define the following three-phase symmetrical quantities (the phase angle is related to phase L1): Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 173
ReverseX 29.60 Ð ç ÷ ° = ç ÷ ° = - ° arctan arctan 90.56 è ø è ø ReverseR 0.29 (Equation 68) EQUATION14068 V1 EN frequency of V = 50 Hz Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 174
ç ÷ ° = ç ÷ ° = - ° arctan arctan 90.56 è ø è ø ReverseR 0.29 (Equation 72) EQUATION14068 V1 EN frequency of V = 50 Hz = 0 A Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 175
= 180º frequency of I = 50.5 Hz Expected result: the protection function does not issue either start or trip. After each test it is possible to download and study the related disturbance recording. Transformer protection RET670 2.2 ANSI Commissioning manual...
A three-phase fault with zero impedance and a three-phase fault with an impedance corresponding to the whole line is applied. This fault shall cause an instantaneous trip and result in a TRIP indication. 11.4.13.1 Activating ZCVPSOF externally Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
Trip No Trip 231a No Trip Trip Trip No Trip No Trip Trip 312a Trip No Trip No Trip Trip No Trip Trip 321a No Trip Trip No Trip Trip No Trip Trip Transformer protection RET670 2.2 ANSI Commissioning manual...
If the measurement of the operating characteristics runs under constant voltage conditions, ensure that the maximum continuous current in an IED does not exceed four times its rated value. To verify the zone 1 mho characteristic, at least two points must be tested. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 180
P1, P2, P3 and P4. For each test point, observe that the output signals, PICKUP and PU_Z1 are activated where x refers to the actual phase to be tested. After the trip time delay for the zone 1 has elapsed, the signals TRIP and TRZ1 shall be activated. Transformer protection RET670 2.2 ANSI Commissioning manual...
11.4.15.2 Completing the test Continue to test another function or end the testing by setting the parameter TestMode to Disabled under Main menu/Tests/IED test mode/1: TESTMODE. If another function Transformer protection RET670 2.2 ANSI Commissioning manual...
IP>> is in between IP>>Min and IP>>Max. Increase the injected current in the Ln phase until the TR_A (TR_B or TR_C) signal appears. Switch the fault current off. Transformer protection RET670 2.2 ANSI Commissioning manual...
If 1 out of 3 currents are chosen for operation: Connect the injection current to phases A and neutral. If 2 out of 3 currents are chosen for operation: Connect the injection current into phase A and out from phase B. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 185
11. Repeat the above described tests for the higher set stages. 12. Check that pickup and trip information is stored in the event menu . Transformer protection RET670 2.2 ANSI Commissioning manual...
TRIP signal appears. Disable the fault current Do not exceed the maximum permitted overloading of the current circuits in the IED. Compare the measured operating current with the set value. Transformer protection RET670 2.2 ANSI Commissioning manual...
Block lower set steps when testing higher set steps according to the instructions that follow. Connect a trip output contact to a timer. Set the injected current to 200% of the trip level of the tested step, switch on the current and check the time delay. Transformer protection RET670 2.2 ANSI Commissioning manual...
Inject pure negative sequence current, that is, phase currents with exactly same magnitude, reversed sequence and exactly 120° phase displaced into the IED with an initial value below negative sequence current pickup level. No output signals should Transformer protection RET670 2.2 ANSI Commissioning manual...
Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. 11.5.6 Sensitive directional residual overcurrent and power protection SDEPSDE (67N) Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". Transformer protection RET670 2.2 ANSI Commissioning manual...
Assume that φ´ is the phase angle between injected voltage (3V ) and current (3I i.e. φ´ = RCADir-φ. Change φ´ to for example 45 degrees. Increase the injected current until the function trips. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 191
UNREL is activated, which is visible in the Application Configuration in PCM600 when the IED is in online mode. Compare the voltage with the set value VNRelPU . Continue to test another function or complete the test by setting the test mode to Disabled. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 193
Inject current until the function picks up, and make sure that the trip power is equal to the SN_PU setting for the set directional element. Note that for pick-up, both the injected current and voltage must be greater than the set values INRelPU and VNRelPU respectively. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 194
Compare the result with the expected value. The expected value depends on whether definite or inverse time was selected. Continue to test another function or complete the test by setting the test mode to Disabled. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 195
Measure that the trip voltage is equal to the VN_PU setting. The function activates the PICKUP and PUVN signals. Measure the trip time by injecting a voltage 1.2 times set VN_PU trip value. Compare the result with the set tVN trip value. Transformer protection RET670 2.2 ANSI Commissioning manual...
10. Connect a trip output contact to the timer and monitor the output of contacts ALARM1 and ALARM2 to digital inputs in test equipment. Read the heat content in the thermal protection from the local HMI and wait until the content is zero. Transformer protection RET670 2.2 ANSI Commissioning manual...
11.5.8.1 Checking the phase current trip value, The check of the Pickup_PH current level is best made in FunctionMode = Current and BuTripMode = 1 out of 3 or 2 out of 4. Transformer protection RET670 2.2 ANSI Commissioning manual...
Disconnect AC and BFI_3P input signals. 11.5.8.4 Verifying the re-trip mode Choose the mode below, which corresponds to the actual case. In the cases below it is assumed that FunctionMode = Current is selected. Transformer protection RET670 2.2 ANSI Commissioning manual...
Interrupt the current, with a margin before back-up trip time, t2. It may be made at issue of re-trip command. Check that re-trip is achieved, if selected, but no back-up trip is obtained. Disconnect AC and BFI_3P input signals. Transformer protection RET670 2.2 ANSI Commissioning manual...
11.5.8.6 Verifying instantaneous back-up trip at CB faulty condition Applies in a case where a signal from CB supervision function regarding CB being faulty and unable to trip is connected to input 52FAIL. Transformer protection RET670 2.2 ANSI Commissioning manual...
Apply the fault condition, including initiation of CCRBRF (50BF), with current above the set Pickup_PH value. Check that the re-trip, if selected, and back-up trip commands are achieved. Disconnect injected AC and BFI_3P input signals. Transformer protection RET670 2.2 ANSI Commissioning manual...
Compare the measured time with the set value tTrip. Reset the EXTPDIND input. Activate the BLKDBYAR binary input. This test should be performed together with Autorecloser SMBRREC (79). Activate the EXTPDIND binary input. Transformer protection RET670 2.2 ANSI Commissioning manual...
Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.5.10.1 Verifying the settings The underpower protection shall be set to values according to the real set values to be used. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 204
= × × PosSeq PosSeq (Equation 82) EQUATION2057-ANSI V1 EN × (Equation 83) EQUATION2058-ANSI V1 EN × (Equation 84) EQUATION2059-ANSI V1 EN × (Equation 85) EQUATION2060-ANSI V1 EN Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
The overpower protection shall be set to values according to the real set values to be used. The test is made by means of injection of voltage and current where the amplitude of both Transformer protection RET670 2.2 ANSI Commissioning manual...
HMI that the output signal TRIP from the BRCPTOC (46) function block is equal to the logical 0. Set the measured current (fault current) in one phase to about 110% of the set operating current Pickup_PH. Transformer protection RET670 2.2 ANSI Commissioning manual...
SCB). It will be also assumed that all other settings have values as shown in the setting example in the application manual for this SCB. Test equipment Transformer protection RET670 2.2 ANSI Commissioning manual...
Stop injection of all currents (that is, set all currents back to 0A). Check that all above mentioned function binary output signals now have logical value zero. Repeat above steps 1-7 for phase B and phase C. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 209
Check that function binary output signals PU_QOL_A and PU_QOL are set to one. Check that function binary output signals TRQOL and TRIP are set to one after the set time under parameter tQOL (for example, 60s for this SCB) has expired. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 210
Procedure to test inverse time delayed step: The following points on the inverse curve are defined per relevant IEC/ANSI standards for time multiplier value set to k_HOL_IDMT=1.0 UpeakRMS [pu] 1.15 Time [s] 1800 0.12 Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 211
The following formula can be used to calculate required current RMS value in percent at the desired injection frequency in order to archive voltage percentage value given in the above table: =× injected rated (Equation 90) EQUATION2274-ANSI V1 EN Transformer protection RET670 2.2 ANSI Commissioning manual...
No output signals should be activated. Note: If it is difficult to obtain pure negative sequence current for the secondary injection test, a current corresponding to the two phase short-circuit condition can be Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 213
1000 A, IBase is 1000 A, and the following secondary currents are applied: Ampl = 1.1 A Angl = 15 deg Ampl = 0.6 A Angl = 97 deg Ampl = 1.3 A Angl = -135 deg Transformer protection RET670 2.2 ANSI Commissioning manual...
Picup Curr VDepFact IBase × × × CTprim (Equation 91) ANSI13000291 V1 EN Second part of the characteristic (25% of VBase ≤ Restrain voltage ≤ VHighLimit/ 100*VBase), valid when setting parameter VDepMode = Slope: Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 215
VB: Ampl = 50 / √3; Angle = 240° • VC: Ampl = 100 / √3; Angle = 120° Last section of the characteristic: If VDepMode = either Slope or Step, the minimum measured phase-to-phase voltage is higher than VHighLimit/100*VBase: Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 216
Taking into account the above explanation, inject the voltages related to the last part of the characteristic and inject a current IA 200% higher than the set operation level, and check the trip time delay. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 217
19. Measure the definite time delay for the TRUV and TRIP signals and compare it with the set value tDef_UV. 20. Check that pickup and trip information is stored in the event menu. Transformer protection RET670 2.2 ANSI Commissioning manual...
Instantaneously decrease the voltage in one phase to a value about 20% lower than the measured trip value. Measure the time delay for the TRIP signal, and compare it with the set value. Transformer protection RET670 2.2 ANSI Commissioning manual...
Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. 11.6.2 Two step overvoltage protection OV2PTOV (59) Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.6.2.1 Verifying the settings Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
TD1 is set to 0.05 s (default value), then the TRST1 and TRIP signals trip at a time equal to 0.250 s ± tolerance. Repeat the test for Step 2 of the function. Transformer protection RET670 2.2 ANSI Commissioning manual...
1.3 · Pickup1. 14. Finally check that PICKUP and TRIP information is stored in the event menu. Transformer protection RET670 2.2 ANSI Commissioning manual...
Apply voltage higher than the highest set value of VDTrip, V1Low and V2Low to the V1 three-phase inputs and to one phase of the V2 inputs according to figure 48. The voltage differential PICKUP signal is set. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 224
The connections to V1 must be shifted to test another phase. (VA to VB, VB to VC, VC to VA) Check of V2Low Procedure Connect voltages to the IED according to valid connection diagram and figure 49. Transformer protection RET670 2.2 ANSI Commissioning manual...
Check V2 blocking level by comparing the voltage level at reset with the set undervoltage blocking V2Low. 11.6.5.2 Check of voltage differential trip and alarm levels Procedure Connect voltages to the IED according to valid connection diagram and figure 50. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 226
PICKUP with the set trip level VDTrip. Repeat steps to check the other phases. Observe that the connections to V1 must be shifted to test another phase. (VA to VB, VB to VC, VC to VA) Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
The test above can be repeated to check the time to reset. The tests above can be repeated to test the frequency dependent inverse time characteristic. Verification of the low voltage magnitude blocking Transformer protection RET670 2.2 ANSI Commissioning manual...
Measure the time delay for the TRIP signal, and compare it with the set value. Note that the measured time consists of the set value for time delay plus minimum trip time of the pickup function (80 - 90 ms). Transformer protection RET670 2.2 ANSI Commissioning manual...
PickupFreqgrad, and check that the PICKUP signal appears. Note the trip value and compare it with the set value. Increase the frequency to rated operating conditions, and zero rate-of-change. Transformer protection RET670 2.2 ANSI Commissioning manual...
Due to the versatile possibilities of CVGAPC itself, but also the possibilities of logic combinations in the application configuration of outputs from more than one CVGAPC function block, it is hardly possible to define a fully covering general commissioning test. Transformer protection RET670 2.2 ANSI Commissioning manual...
Trip value measurement The current restraining value has also to be measured or calculated and the influence on the operation has to be calculated when the testing of the trip value is done. Transformer protection RET670 2.2 ANSI Commissioning manual...
CTWYEpoint configuration parameter is set to ToObject. If reverse directional feature is selected or CTWYEpoint configuration parameter is set to FromObject, the angle between current and polarizing voltage shall be set equal to rca-dir+180°. Transformer protection RET670 2.2 ANSI Commissioning manual...
"Preparing the IED to verify settings". Values of the logical signals for CCSSPVC are available on the local HMI under Main menu/Tests/Function status/Secondary system supervision/ CurrentCircuitSupervision(87,INd/I)/CCSSPVC(87;INd/I):x, where x = 1, 2 and 3. Transformer protection RET670 2.2 ANSI Commissioning manual...
Simulate normal operating conditions with the three-phase currents in phase with their corresponding phase voltages and with all of them equal to their rated values. Connect the nominal dc voltage to the 89bS binary input. Transformer protection RET670 2.2 ANSI Commissioning manual...
Slowly decrease the measured voltage in one phase until the BLKV signal appears. Record the measured voltage and calculate the corresponding negative-sequence voltage according to the equation (observe that the voltages in the equation are phasors): Transformer protection RET670 2.2 ANSI Commissioning manual...
Consider that the set value 3I2< is in percentage of the base current IBase. 11.9.2.3 Measuring the trip value for the zero-sequence function Measure the trip value for the zero-sequence function, if included in the IED. Transformer protection RET670 2.2 ANSI Commissioning manual...
This is the point at which the dead line condition is detected. Check the value of the decreased voltage with the set value VDLDPU (VDLDPU is in percentage of the base voltage VBase). Transformer protection RET670 2.2 ANSI Commissioning manual...
PU_DV or PU_DI are activated. 10. Check that the pickup output signals for the current and voltage phases 2 and 3 are activated by changing the magnitude of the voltage and current for phases 2 and 3. Transformer protection RET670 2.2 ANSI Commissioning manual...
VSealIn level. MAINFUF signal should not reset. Slowly increase measured voltage to the value slightly above VSealIn until MAINFUF signal resets. Record the measured voltage and compare with the set value VSealIn. Transformer protection RET670 2.2 ANSI Commissioning manual...
Use the set voltages instead of what is indicated below. Figure shows the general test connection principle, which can be used during testing. This description describes the test of the version intended for one bay. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 243
V-Bus Ph/N V-Bus Ph/Ph Input Phase A,B,C AB,BC,CA V-Line VMeasure Ph/N Ph/Ph Input Phase A,B,C AB,BC,CA ANSI05000480-3-en.vsd ANSI05000480 V3 EN Figure 51: General test connection with three-phase voltage connected to the line side Transformer protection RET670 2.2 ANSI Commissioning manual...
FreqDiffMin. The test procedure below will depend on the settings used. Input STARTSYN must be activated during the test. FreqDiffMax = 50.2 Hz FreqDiffMin = 50.01 Hz tBreaker = 0.080 s Apply voltages Transformer protection RET670 2.2 ANSI Commissioning manual...
The settings used in the test shall be final settings. The test shall be adapted to site setting values instead of values in the example below. Test with no voltage difference between the inputs. Test with a voltage difference higher than the set VDiffSC. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 246
V-Bus, between ± dφ degrees, the user can check that the two outputs are activated for a phase difference lower than the set value. It should not trip for other values. See figure 53. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 247
If a modern test set is used, the frequency can be changed continuously. Testing the reference voltage Use the same basic test connection as in figure 51. Transformer protection RET670 2.2 ANSI Commissioning manual...
The test should verify that the energizing check function trips for a low voltage on the V- Bus and for a high voltage on the V-Line. This corresponds to an energizing of a dead bus to a live line. Transformer protection RET670 2.2 ANSI Commissioning manual...
Testing the voltage selection for single CB arrangements This test should verify that the correct voltage is selected for the measurement in the SESRSYN function used in a double-bus arrangement. Apply a single-phase voltage of Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 250
SESRSYN 3 all are in the same IED. If SESRSYN 3 is in another IED, WA1 will be considered as WA2 and LINE2 as LINE1. The voltage is selected by activation of different inputs in the voltage selection logic as shown in table and figure 54. Transformer protection RET670 2.2 ANSI Commissioning manual...
In such cases, where there is a mismatch, the user is advised to make a complete cycle of block/unblock operations to align the statuses. Transformer protection RET670 2.2 ANSI Commissioning manual...
Confirm power system base quantities I1Base, I2Base, VBase. Main menu/Settings/Setting Group N/Control/ TransformerVoltageControl(ATCC,90)/TR1ATCC:x/TR8ATCC:x/General Main menu/Settings/Setting Group N/Control/ TransformerVoltageControl(ATCC,90)/TR1ATCC:x • Confirm that the setting for short circuit impedance Xr2 for TR1ATCC (90) or TR8ATCC (90) is in accordance with transformer data: Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 254
Ia, Ib, Ic or the two-phase quantities Ii and Ij, or single-phase current Ii. Transformer protection RET670 2.2 ANSI Commissioning manual...
11.10.3.2 Check the activation of the voltage control operation Confirm Transformer Tap Control = Enable and Transformer Voltage Control = Enable • Direct tap change control Main menu/Settings/Setting Group N/Control/ TransformerTapChanger(YLTC,84)/TCMYLTC:x/TCLYLTC:x/Operation Transformer protection RET670 2.2 ANSI Commissioning manual...
Raise the voltage 1% above the upper deadband limit V2 and wait for the issue of a lower command from the voltage control after the expiry of a constant or inverse time delay set by t1. Detection of this command will involve locating the allocated Transformer protection RET670 2.2 ANSI Commissioning manual...
HMI. For an alarm condition, the voltage regulation function is not blocked and a lower command should be issued from the IED. 11.10.3.6 Check the overcurrent block function Transformer protection RET670 2.2 ANSI Commissioning manual...
When all secondary phase-to-ground voltages are available, use the positive- sequence components of voltage and current. By separation of real and imaginary parts: × × vl re vb re rline il re xline il im (Equation 109) EQUATION2083-ANSI V1 EN Transformer protection RET670 2.2 ANSI Commissioning manual...
For the transformers connected in the parallel group, confirm that OperationPAR is set to MF. For parallel operation, it is also recommended to confirm for parallel group membership, defined by setting TnRXOP in the local HMI under Main menu/ Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 260
Circulating current voltage regulation This instruction for confirmation of circulating current voltage regulation assumes two transformers in the parallel group. Setting confirmation through secondary injection requires calculation of circulating currents for each transformer based on impedance Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 261
Confirm the settings for Ci (Compensation Factor) and Xi (Transformer Short Circuit Impedance). Using these setting values and the measured quantity of circulating current from the local HMI (Icc_i), calculate the value for circulating current voltage adjustment Vci. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 262
Transformer 2 so that the magnitude of calculated circulating current will cause a raise command to be issued for Transformer 2 and a lower command for Transformer 1. Magnitude and direction of circulating currents measured for each Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 263
TR8ATCC (90) for all transformers connected in the parallel group, which can be confirmed through interrogation of the local HMI. Confirm that the automatic voltage control for tap changer, parallel control function TR8ATCC (90) responds in accordance with the setting for CircCurrBk. Transformer protection RET670 2.2 ANSI Commissioning manual...
ZCPSCH (85) Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". Check the scheme logic during the secondary injection test of the impedance or overcurrent protection functions. Transformer protection RET670 2.2 ANSI Commissioning manual...
Apply a fault condition within the permissive zone. Check that trip time complies with the zone timers and that correct trip outputs, external signals, and indications are obtained for the actual type of fault generated. 11.11.1.3 Testing blocking scheme Transformer protection RET670 2.2 ANSI Commissioning manual...
10. Check that the trip time from the forward directed zone used for scheme communication tripping complies with the zone timer and that correct trip outputs, external signals, and indications are obtained for the actual type of fault generated. Transformer protection RET670 2.2 ANSI Commissioning manual...
Apply healthy normal load conditions to the IED for at least two seconds. Apply a fault condition within the permissive zone. Check that correct trip outputs, external signals, and indications are obtained for all the actual types of fault generated. Transformer protection RET670 2.2 ANSI Commissioning manual...
(plus relay measuring time). Check that the other zones operate according to their zone times and that a send (CS_x) signal is only obtained for the reverse zone. Activate the IED receive (CRLx) signal. Transformer protection RET670 2.2 ANSI Commissioning manual...
Checking of current reversal The reverse zone timer must not operate before the forward zone fault is applied. The user might need to block the reverse zone timer setting during testing of current reversal. Transformer protection RET670 2.2 ANSI Commissioning manual...
For phase A-G fault, set these parameters: Table 35: Phase A-G parameter values Phase I (Amps) Phase-angle (Deg) V (Volts) Phase-angle (Deg) Set less than UPN<PU27PN 69.3 69.3 If wanted, change all settings cyclically for other faults (BG andCG). Transformer protection RET670 2.2 ANSI Commissioning manual...
The current reversal and weak- end-infeed functions shall be tested together with the permissive scheme. 11.11.4.1 Testing the directional comparison logic function Blocking scheme Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 272
Switch the fault current on, (110% of the set operating current) and wait longer than the set value tCoord. No TRIP signal should appear, and the CS binary output should be activated. Switch the fault current off. Activate the CR binary input. Transformer protection RET670 2.2 ANSI Commissioning manual...
First, test the four step residual overcurrent protection function EF4PTOC (51N/67N) and then the current reversal and weak-end infeed logic according to the corresponding instructions. Then continue with the instructions below. 11.11.5.1 Testing the current reversal logic Transformer protection RET670 2.2 ANSI Commissioning manual...
Switch off the current and check that the ECHO and CS appear on the corresponding binary output during 200ms after resetting the directional element. Switch off the CRL binary input. Activate the BLOCK binary input. Activate the CRL binary input. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 275
11. Inject current in one phase to about 110% of the set trip current (INDir). 12. Activate the CRL binary input. No ECHO and TRWEI should appear. 13. Abruptly reverse the current to 65° lagging the voltage to trip the forward directional element. Transformer protection RET670 2.2 ANSI Commissioning manual...
(79). The function must issue a three-pole trip in all cases, when trip is initiated by any protection or some other built-in or external function. The following functional output signals must always appear simultaneously: TRIP, TR_A, TR_B, TR_C and TR3P. Transformer protection RET670 2.2 ANSI Commissioning manual...
Initiate different single-phase-to-ground faults one at a time. Take an adequate time interval between faults into consideration, to overcome a reset time, which is activated by the autorecloser function SMBRREC (79). Only a Transformer protection RET670 2.2 ANSI Commissioning manual...
CLLKOUT should not be set. Activate the automatic lockout function, set AutoLock = Enabled and repeat. Besides the TRIP outputs, CLLKOUT should be set. Reset the lockout signal by activating the reset lockout (RSTLKOUT) signal. Transformer protection RET670 2.2 ANSI Commissioning manual...
PresAlmLimit or activate binary input signal SENPRESALM, check that outputs PRESALM and ALARM are activated after a set time delay of tPressureAlarm. Gas pressure lockout input SETPLO can be used to set PRESLO. Transformer protection RET670 2.2 ANSI Commissioning manual...
= 1, 2,..4. Check that the input logical signal BLOCK is logical zero and that on the local HMI, the logical signals LVLALM, LVLLO, TEMPALM, TEMPLO, ALARM and LOCKOUT are logical zero. Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TestMode setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
5.4. Check the circuit breaker is in INVDPOS if auxiliary contacts read same value or CB is open and inject the current in selected phase more than AccStopCurr set value. Test of remaining life of CB Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 283
9.1. Test the actual set value defined by SpChAlmTime. 9.2. Enable SPRCHRST input. Also activate SPRCHRD after a time greater than set time SpChAlmTime. 9.3. At this condition, SPCHALM is activated. 10. Test of CB gas pressure indication Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the Test mode setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
WrnHPTmpLev2 level during injection. Monitor the signal WARNING2 until it appears on the corresponding binary output. Compare the measured temperature (HPTMPMAX) with WrnHPTmpLev2 setting. Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the Test mode setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
After some time (multiple of minute) remove the current and voltage input from CVMMXN function block. Check the EAFACC and ERFACC output in the next 1 minute cycle for the retaining the same value. Transformer protection RET670 2.2 ANSI Commissioning manual...
Completing the test Continue to test another function or end the test by changing the TESTMODE setting to Disabled. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 ANSI Commissioning manual...
HMI under • Self-supervision status: Main menu/Diagnostics/Internal events • Status for inputs and outputs: Main menu/Test/Function status, browse to the function group of interest. • Remote communication related signals: Main menu/Test/Function status/ Communication/Remote communication Transformer protection RET670 2.2 ANSI Commissioning manual...
Figure 55: Test of RTC with I/O 11.17 Basic IED functions 11.17.1 Parameter setting group handling SETGRPS Prepare the IED for verification of settings as outlined in section "Preparing for test" this chapter. Transformer protection RET670 2.2 ANSI Commissioning manual...
The following procedure is used to return to normal operation. Navigate to the test mode folder. Change the Enable setting to Disable. Press the 'E' key and the left arrow key. Answer YES, press the 'E' key and exit the menus. Transformer protection RET670 2.2 ANSI Commissioning manual...
Vset voltage and ATCC increases the voltage in order to achieve the correct system voltage at the load point. Confirm the PST settings for Rline and Xline. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 294
RL and XL are the settings given in primary system ohms. ANSI06000487-2-en.vsd For inductive load, the Bus Voltage should be higher than the Load Voltage. If not, current circuits are incorrect and must be reversed. Incorrect current polarity may be an issue with Transformer protection RET670 2.2 ANSI Commissioning manual...
Check the overcurrent blocking level (Iblock) in Main menu/Settings/General settings/Control/TransformerVoltageControl(ATCC,90)/TR8ATCC:x/ TCCtrl/Iblock. Check that the circulating current blocking (OperCCBlock) is set On, and the check the correct settings for circulating current limit (CircCurLimit) in Main menu/ Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 296
T2 and T3. The currents measured at T2 and T3 will ideally be about the same values. If the voltage is close to the upper limit of the Transformer protection RET670 2.2 ANSI Commissioning manual...
Set the control mode to Manual for each transformer in the parallel control group Open the test display for Transformer Voltage Control on the LHMI in Main menu/ Test/Function status/Control/TransformerVoltageControl (ATCC, 90). Transformer protection RET670 2.2 ANSI Commissioning manual...
After the test is completed and relevant disturbance records are saved to document the test, go to Main menu/Clear on the local HMI and clear all LEDs, the process eventlist and disturbances from the IED. Transformer protection RET670 2.2 ANSI Commissioning manual...
• load current > 5% of base current • Otherwise the settings IMinOpPG and IMinOpPP for ZDRDIR or ZDMRDIR are available under the HMI menu: Main menu/ Settings/IED Settings/Impedance protection/ DirectionalImpedance Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 300
(verify that no wrong negation has been set; the setting name is: Negation). If the directional function shows “No direction” for all the three phases it can mean that the load current is below the minimum operating current or that the load Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 301
(active power). Usually it is enough to look at the resistive values to get information of the load direction, that must anyway be compared with the indication given by external equipment measuring the same power flow. Transformer protection RET670 2.2 ANSI Commissioning manual...
The periodicity of all tests depends on several factors, for example the importance of the installation, environmental conditions, simple or complex equipment, static or electromechanical IEDs, and so on. The normal maintenance practices of the user should be followed. However, ABB's recommendation is as follows: Every second to third year Transformer protection RET670 2.2 ANSI...
ABB protection IEDs are preferably tested by aid of components from the COMBITEST testing system or FT test systems described in information B03-9510 E. Main components are RTXP 8/18/24 test switch usually located to the left in each protection IED and RTXH 8/18/24 test handle, which is inserted in test switch at secondary testing.
HMI. At the end of the secondary injection test it should be checked that the event and alarm signalling is correct by activating the events and performing some selected tests. Transformer protection RET670 2.2 ANSI Commissioning manual...
IED. The service values are checked on the local HMI or in PCM600. Ensure that the correct values and angles between voltages and currents are recorded. Also check the direction of directional functions such as Distance and directional overcurrent functions. Transformer protection RET670 2.2 ANSI Commissioning manual...
Thus a list should be prepared of all items disturbed during test so that all can be put back into service quickly and without overlooking something. It should be put back into service item by item and signed by the responsible engineer. Transformer protection RET670 2.2 ANSI Commissioning manual...
Time synch Ready No problem detected. None. Time synch Fail No time synchronization. Check the synchronization source for problems. If the problem persists, contact your ABB representative for service. Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Ready (I/O module name) Fail I/O modules has failed. Check that the I/O module has been configured and connected to the IOP1- block. If the problem persists, contact your ABB representative for service. 15.2 Fault tracing 15.2.1 Internal fault indications...
The IED has full functionality without time synchronization. 15.2.2 Using front-connected PC When an internal fault has occurred, extensive information about the fault can be retrieved from the list of internal events available in the SMS part: Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 312
All disturbances in Disturbance report cleared The events in the internal event list are time tagged with a resolution of 1ms. This means that, when using the PC for fault tracing, it provides information on the: Transformer protection RET670 2.2 ANSI Commissioning manual...
AP1: MU1_9201 svID: <ABB_MU0101> Time diff: IED vs Sampled value <Access Point><Hardware Module Identifier><svID> Where the Hardware Module Identifier is the same as given in PCM600, e.g. AP1: MU1_9201 svID: <ABB_MU0101> Table continues on next page Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 314
The factory image is older and does not contain the latest updates and fixes. Please reboot the IED. If the problem persists, update the OEM firmware or replace the board. Transformer protection RET670 2.2 ANSI Commissioning manual...
An alternative is to open the IED and send only the faulty circuit board to ABB for repair. When a printed circuit board is sent to ABB, it must always be placed in a metallic, ESD- proof, protection bag.
15.4 Repair support If an IED needs to be repaired, the whole IED must be removed and sent to an ABB Logistic Center. Please contact the local ABB representative to get more details. 15.5 Maintenance The IED is self-supervised.
British Standards Binary signal transfer function, receiver blocks Binary signal transfer function, transmit blocks C37.94 IEEE/ANSI protocol used when sending binary signals between IEDs Controller Area Network. ISO standard (ISO 11898) for serial communication Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 318
Carrier send Current transformer Communication unit CVT or CCVT Capacitive voltage transformer Delayed autoreclosing DARPA Defense Advanced Research Projects Agency (The US developer of the TCP/IP protocol etc.) DBDL Dead bus dead line Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 319
Modular 20 channel telecommunication system for speech, data and protection signals FOX 512/515 Access multiplexer FOX 6Plus Compact time-division multiplexer for the transmission of up to seven duplex channels of digital data over optical fibers Flexible product naming Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 320
IEC 61850 Substation automation communication standard IEC 61850–8–1 Communication protocol standard IEEE Institute of Electrical and Electronics Engineers IEEE 802.12 A network technology standard that provides 100 Mbits/s on twisted-pair or optical fiber cable Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 321
Ingression protection, according to IEC 60529, level IP54-Dust-protected, protected against splashing water. Internal failure signal IRIG-B: InterRange Instrumentation Group Time code format B, standard 200 International Telecommunications Union Local area network LIB 520 High-voltage software module Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 322
The relay “sees” the fault but perhaps it should not have seen it. Peripheral component interconnect, a local data bus Pulse code modulation PCM600 Protection and control IED manager PC-MIP Mezzanine card standard PCI Mezzanine card Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 323
System configuration tool according to standard IEC 61850 Service data unit Small form-factor pluggable (abbreviation) Optical Ethernet port (explanation) Serial communication module. SMA connector Subminiature version A, A threaded connector with constant impedance. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 324
BNC connector Trip (recorded fault) TPZ, TPY, TPX, TPS Current transformer class according to IEC Transformer Module. This module transforms currents and voltages taken from the process into levels suitable for further signal processing. Transformer protection RET670 2.2 ANSI Commissioning manual...
Page 325
A digital signalling interface primarily used for telecom equipment Three times zero-sequence current.Often referred to as the residual or the ground-fault current Three times the zero sequence voltage. Often referred to as the residual voltage or the neutral point voltage Transformer protection RET670 2.2 ANSI Commissioning manual...