Page 1
FusionModule2000 Smart Modular Data Center V500R002 Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) Issue Date 2017-06-30 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) About This Document About This Document Purpose This document describes how to install the smart modular data center (Smart Module for short) in the single-row aisle containment scenario.
Page 4
Added the descriptions about how to install the base, access control system on the sliding door, and the smart module in the scenario with a column. Issue 02 (2016-08-30) Updated the product name from IDS2000 to FusionModule2000. Issue 01 (2016-06-07) This issue is the first official release.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) Contents Contents About This Document ......................ii 1 Installation Preparations....................... 1 1.1 Precautions for Transportation ............................. 1 1.2 Unpacking and Acceptance ..............................2 1.3 Installation Environment Requirements ..........................3 1.4 Site Requirements .................................
Page 6
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) Contents 3.1.3.7 Preparing Cables ................................34 3.1.3.8 (Engineering Procurement) Water Softener ........................ 36 3.1.3.9 Checking Nitrogen Pressure ............................37 3.1.3.10 Removing the Transport Fasteners ..........................38 3.2 Removing Pallets ................................
Page 7
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) Contents 5.2.1.2 800 mm Wide Control Skylight ........................... 91 5.2.1.3 600 mm Wide Flat or Rotating Skylight ........................92 5.2.1.4 800 mm Wide Flat or Rotating Skylight ........................93 5.2.1.5 300 mm Wide Flat Skylight ............................
Page 8
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) Contents 7.9 Installing Monitoring Components on Cable Troughs ....................162 7.9.1 Installing a Smart ETH Gateway ..........................162 7.9.2 (Optional) Installing an ETH Converter........................164 7.10 Installing Temperature Sensors ............................165 7.11 Rules for Deploying T/H Sensors ..........................166...
Page 9
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) Contents A.4.1 Scenario Description..............................209 A.4.2 Installation Process for Scenarios with Columns .......................215 A.4.3 Installing a Cabinet Bottom Sealing Plate........................215 A.4.4 Installing Sealing Plates Near the Aisle ........................216 A.4.5 Installing the Adjustable Skylight ..........................218...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations Installation Preparations 1.1 Precautions for Transportation Precautions for Air Conditioner Transportation Only trained personnel are allowed to move the cabinet. Use a pallet truck to transport the cabinet secured to a wooden support to the installation position.
Step 1 Unpack the carton labeled "Contain Packing List" and take out the Packing List. Step 2 Check all items against the Packing List. Step 3 If an item is incorrect or missing, contact Huawei technical support. Step 4 If any item is damaged, fill in the Cargo Replacement Application Form and report it.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations Step 5 Sign on the Packing List with the customer after verifying that all required items are delivered. Step 6 Store the items properly.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations 1.4 Site Requirements Equipment Room Height Requirement The net height of an equipment room must not be lower than 2600 mm in the case of a single-row aisle containment.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations Documentation Purpose Obtaining Method (Remarks) iBAT 2.0-CIM01C2 User Describes the installation, Click Download. Manual cable connection, and power-on operations for the CIM and BIM.
Page 18
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations Name, Specifications, and Appearance Adjustable wrench Socket wrench Hex key Box-end wrench (6") M4/M6/M8/M12 (M6, M8, and M12) Torque wrench (28...
Page 19
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations Name, Specifications, and Appearance Crimping tool Wire stripper Hydraulic pliers Wire clippers Cable ties Multimeter Electroprobe Brush Claw hammer Vacuum cleaner...
Page 20
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations Table 1-5 Transportation and unpacking tools Tool Appearance, Specifications, and Name Pallet truck Diesel forklift Lifting rope (bearing Lever (bearing capacity ≥ 400 kg) capacity ≥...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 1 Installation Preparations Tool Appearance, Specifications, and Name Reducing valve a: For equipment with humidifiers, ensure that the water pipe thread sealant is able to resist temperatures higher than 85°...
Only trained and qualified personnel who fully understand basic safety precautions are allowed to install and operate a modular data center. Huawei will not be liable for any consequence caused by the violation of this document. The requirements are as follows: ...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 2 Scenario Description Scenario Description Figure 2-1 shows the floor plan of the smart module A single-row aisle containment. The PDC is an integrated UPS. Figure 2-2 shows the exterior of the single-row aisle containment of the smart module.
Page 26
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 2 Scenario Description Figure 2-1 Floor plan of a single-row cold aisle containment (with 1200 mm deep IT cabinets) Figure 2-2 Exterior of the single-row aisle containment...
Optional: materials that can be purchased from Huawei or any other vendor (if you have ordered the materials from Huawei, you do not need to purchase them elsewhere). For details about the specifications of such materials to be purchased, see the following sections.
Page 28
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations measure the external surface temperature of the refrigerant container, and connect a pressure gauge to the container to measure its internal pressure. Determine the saturation pressure that corresponds to the measured external surface temperature according to Table 3-1 and calculate the deviation from the measured internal pressure.
1.27 2.15 3.1.2.2 Refrigerant Oil Danfoss 160SZ refrigerant oil is recommended. It can be purchased by Huawei or by the customer after confirmed by Huawei. Whether refrigerant oil is needed depends on the length (L) of the single-way piping between air conditioner indoor and outdoor units.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-4 Pagoda connector (unit: mm) 3.1.2.5 Pipe Support Figure 3-5 shows supports for refrigerant pipes and water pipes. The actual appearance of the supports will be different based on onsite situations.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Table 3-4 Cable specifications Name Specifications Quantity Remarks Indoor unit Four-core cable : electrical power cable-600 1 PCS (The Optional...
Page 34
If they do not exist, contact Huawei technical support. If they exist, remove each valve bonnet and use it to press the valve plugs in turn. If air is exhausted, the system is working properly. If no air is exhausted, contact Huawei technical support.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-7 Needle valves (1) Low-pressure needle (2) Liquid pipe needle (3) Discharge pipe needle valve valve valve ----End 3.1.2.8 Removing the Transport Fasteners from Floats...
Page 36
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-8 Position of the water tank (1) Water pan (2) Water tank (3) High and low floats Figure 3-9 Positions of high and low floats...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Step 3 Connect the wiring terminal to the high float cable, and place the wiring terminal above the water tank to avoid wetting in the case of water overflow.
3.1.3 Preparing for Installing the NetCol5000-A 25 kW Air Conditioner 3.1.3.1 (Optional) Refrigerant R410A Do not use low-quality refrigerant. Huawei is not responsible for any damage caused by low-quality refrigerant. Follow these suggestions to choose high-quality refrigerant: Use high-quality brands such as DuPont, Daikin, or Honeywell.
Page 39
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations measure the external surface temperature of the refrigerant container, and connect a pressure gauge to the container to measure its internal pressure. Determine the saturation pressure that corresponds to the measured external surface temperature according to Table 3-5 and calculate the deviation from the measured internal pressure.
1.27 2.15 3.1.3.2 (Optional) Refrigerant Oil The recommended refrigerant oil is RL32H/Emkarate. You can purchase it from Huawei or another vendor. The refrigerant oil purchased from another vendor should be confirmed by Huawei. 3.1.3.3 (Optional) Oil Trap and Inverted Trap The operating pressure of the copper pipe, oil trap, and inverted trap should be greater than 4.5 MPa.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Name Copper Pipe Outer Technical Requirements Diameter and Thickness Oil trap 19.1 mm x 1.2 mm The flaring inner diameter of the copper pipe is 19.1 mm, and the necking outer...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations materials Components inside the dashed-line boxes are ports on the equipment. Component 3 is mandatory. Other components are subject to engineering procurement.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.1.3.6 Pipe Support Figure 3-16 shows supports for refrigerant pipes and water pipes. The actual appearance of the supports will be different based on onsite situations.
Page 44
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Applicati Name Technical Specifications Remarks Scenario Indoor Power cable Electrical power cable, 600 V, The length is unit (optional) ZA-RVV, 5 x 6 mm...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Applicati Name Technical Specifications Remarks Scenario M4/OT Bare crimp terminal, OT, 2.5 mm Delivered with the terminal M4, 27 A, tin plating, 16–14 AWG...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-18 Needle valves (1) Low-pressure needle (2) Liquid pipe needle (3) Discharge pipe needle valve valve valve ----End 3.1.3.10 Removing the Transport Fasteners Context ...
Page 48
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Store the removed transport fasteners. They should be reinstalled if the equipment needs to be transported in future. Figure 3-19 Removing the transport fasteners from a compressor ...
Page 49
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-20 Removing a water pan cover Remove the two M4x10 screws from the liquid level detector transport fastener, and remove the transport fastener, as shown in Figure 3-21.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-22 Connecting the interconnection terminal Reinstall the water pan cover. Step 3 Close the front and the rear doors.
Page 51
If any damage is found, notify the carrier immediately. Check that the fittings comply with the packing list. If some fittings are missing or do not comply with the packing list, record the information and contact your local Huawei office immediately.
Page 52
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-23 Removing the L-shaped bracket Ensure that the sliding plates are properly installed in step 2 in Figure 3-23. Otherwise, the sliding plates may shift when the PDC is unloaded.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.2.2 Removing the IT Cabinet Pallet Context The methods for removing pallets are the same for the network cabinet, battery cabinet, and IT cabinet.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.2.3 Removing the NetCol5000-A 35 kW Air Conditioner Pallet Procedure Step 1 After a packed cabinet arrives onsite, unpack the cabinet.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-27 Removing the screws Step 2 Remove the cabinet from the pallet. ----End 3.3 (Optional) Adjusting IT Cabinet Side Plates...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-28 Installing a cabinet side plate ----End Follow-up Procedure After adjusting side plates, remove the labels on the plates.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.5 (Optional) Installing the PDC Tail Frame Context A tail frame is used to increase the depth of a PDC to 1200 mm. Its bill of materials (BOM) number is 21242025.
Page 58
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-30 Securing the tail frame accessories Step 2 Use four M5 tapping screws to secure one upper sealing plate to the tail frame, as shown in Figure 3-32.
Page 59
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-32 Installing the upper sealing plates of a tail frame Step 3 Open the PDC rear door, and remove it, as shown in Figure 3-33.
Page 60
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Step 4 Remove the hinges and connecting plates from the PDC rear door, as shown in Figure 3-34. Put aside the hinges and connecting plates as they are needed in follow-up installation processes.
Page 61
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Align the upper and lower holes before tightening screws. The tail frame side with anchor bolts should face the cabinet bottom.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.6 (Optional) Installing a 600 mm Wide Air Conditioner Enclosure Frame Context To increase the equipment depth to 1200 mm, install enclosure frames whose BOM number is 21242025 on the front doors of air conditioners.
Page 63
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-37 Upper sealing plates of an enclosure frame Figure 3-38 Installing the upper sealing plates of an enclosure frame Step 3 Remove one bolt fastener, four cabinet connecting kits, and two front door mounting kits.
Page 64
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-39 Removing the front door mounting kits Step 4 Secure the enclosure frame. Issue 04 (2017-06-30) Huawei Proprietary and Confidential...
Page 65
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Align the upper and lower holes before tightening screws. The enclosure frame side with anchor bolts should face the cabinet bottom.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.7 (Optional) Installing a 300 mm Wide Air Conditioner Enclosure Frame Context To increase the equipment depth to 1200 mm, install enclosure frames whose BOM number is 21242048 on the front doors of air conditioners.
For detailed dimensions requirements for bases, click Download. If you do not use the bases provided by Huawei, design the bearing requirements for bases according to the service plan.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.8.2 Installing Adjustable Bases 3.8.2.1 Installing a Cabinet Base 3.8.2.1.1 Assembling a Base Procedure Step 1 Adjust the base height.
Page 69
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-44 Tightening height locking bolts Step 2 Assemble the base. Adjust the base depth based on the cabinet depth.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.8.2.1.2 Positioning Bases Procedure Step 1 Determine the correct installation position for the smart module based on the onsite engineering layout diagram.
Page 71
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-47 Positioning the first base Step 5 Use the end cabinet base as the reference and place other cabinet bases.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-49 Positioning holes ----End 3.8.2.1.3 Securing Bases Prerequisites The base has been positioned. Procedure Step 1 Move the base, and drill holes to depths of 52 mm to 60 mm using a hammer drill with a Φ16 drill bit.
Page 73
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-50 Leveling a base Step 4 If a base is not level, put spacers under it, as shown by (2) in Figure 3-50.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations ----End Result After securing bases, ensure that adjacent bases are in close contact with each other and the gap is even.
Page 75
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-53 Removing adjustable feet Move the adjustable feet to the mounting holes on the base according to the depth of the air conditioner.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.8.3.2 Deploying Bases for a 600 mm wide IT Cabinet/Battery Cabinet/Network Cabinet The 600 mm wide fixed bases are used for the 600 mm wide IT cabinet, network cabinet, and battery cabinet.
Page 77
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-56 600 mm wide adjustable base (1) Used for a PDC in a cold aisle (2) Used for an air conditioner in a cold...
Page 78
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-57 Removing adjustable feet Move the adjustable feet to the mounting holes on the base according to the depth of the cabinet.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations 3.8.3.4 Deploying 800 mm Wide Fixed Bases The 800 mm wide fixed bases are used for 800 mm wide IT cabinets and network cabinets.
Page 80
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Support Securing Method supports of the base, and secure the base to 600 mm adjustable base the concrete floor using six expansion bolts.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Figure 3-61 Securing adjacent bases ----End 3.9 Installing Air Conditioner Outdoor Units and Routing Pipes Table 3-10 lists the reference documents for installing air conditioner outdoor units and routing pipes.
Page 82
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 3 Hardware Installation Preparations Device Name Reference NetCol5000-A 35 kW air NetCol5000-A 25 kW&35 kW Air Cooled In-row Precision Air cooled in-row precision Conditioner Quick Guide (600 mm Wide)
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Installing Cabinets 4.1 Installing Cabinets (with Bases) Prerequisites The upper surface of the ESD floor is flush with the upper surface of the base.
Page 84
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Do not remove the anchor bolts. Otherwise, rework is required if the cabinet height does not meet requirements. Anchor bolt adjustment method: Wrench an anchor bolt clockwise to elevate a cabinet leg, or wrench an anchor bolt anticlockwise to lower it.
Page 85
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-2 Interconnecting cabinets Step 4 Secure the cabinets. Figure 4-3 Securing a cabinet Issue 04 (2017-06-30) Huawei Proprietary and Confidential...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets ----End 4.2 Installing Cabinets (Without Bases) Procedure Step 1 Place end cabinets in the marked positions. Figure 4-4 Placing a cabinet Step 2 Level the cabinets.
Page 87
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Do not remove the anchor bolts. Otherwise, rework is required if the cabinet height does not meet requirements. Anchor bolt adjustment method: Wrench an anchor bolt clockwise to elevate a cabinet leg, or wrench an anchor bolt anticlockwise to lower it.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-7 Securing a cabinet ----End 4.3 Installing Cabinet Accessories 4.3.1 (Optional) Taking Out PDU2000 Cables and Industrial Connectors Prerequisites PDU2000s are equipped with industrial connectors.
Page 90
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-8 Taking out PDU2000 industrial connectors Step 2 Lay out the PDU2000 industrial connectors and cables on the cabinet top, and reinstall the rodent-proof mesh.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Follow-up Procedure Before connecting the power plug of a device to the PDU2000, loosen the locking device on the PDU2000. After connecting the power plug, tighten the locking device.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-11 Installing a ground copper bar ----End 4.3.3 (Optional) Installing a Vertical Ground Copper Bar Context The BOM number for the vertical ground copper bar is 21241363.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-12 Installing a vertical ground copper bar ----End 4.3.4 (Optional) Setting a Cabinet Code Lock Context The cabinet code lock can be unlocked with a key or password. If you do not need the password function, you can use a key to unlock the cabinet.
Page 94
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-13 Cabinet code lock (1) Lock base (2) Lock head (3) Wheel (4) Password knob Verifying the Preset Password Step 1 Enter the password and turn the knob for 180 degrees counterclockwise to unlock.
Page 95
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-14 Unlocking with a password ----End Retrieving the Password Step 1 Insert the cabinet key into the lock hole and turn it for 180 degrees counterclockwise to unlock.
Page 96
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-15 Unlocking with a key Step 2 Open the cabinet door, turn the lock head to reveal the rear of the lock head, and turn the key to the initial position.
Page 97
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 4 Installing Cabinets Figure 4-16 Changing the password Step 3 Turn the knob for 15 degrees clockwise. ----End Issue 04 (2017-06-30) Huawei Proprietary and Confidential...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Installing the Contained Aisles 5.1 Installing a Sealing Plate Context Sealing plates are used to seal the aisle. Different types of sealing plates are used for cabinets with different sizes.
Page 99
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-1 Installing a sealing plate Step 2 Place a sealing plate. When placing a sealing plate, keep the smooth plane facing the outside of the contained aisle.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Step 5 Install other sealing plates in the same way. Step 6 Connect adjacent sealing plates using three M6x16 screws with flat washers and nuts, as shown by (3) in Figure 5-1.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-3 800 mm wide control skylight (1) Skylight connective plate (2) Control skylight panel (3) Cable separation panel The 800 mm wide control skylight is used to install monitoring components such as the camera, multi-functional sensor, or smoke detector.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-5 600 mm wide rotating skylight (1) Magnetic lock (2) Skylight connective plate (3) Rotating skylight panel 5.2.1.4 800 mm Wide Flat or Rotating Skylight The BOM numbers of 800 mm wide rotating and flat skylights are the same (21501039).
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles 5.2.2 Securing Skylights Context Install skylights one by one from one end of the smart module based on the onsite engineering layout diagram.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles The number of M6x16 screws must be the same as the number of rivet nuts on the end plane of the skylight connective plates.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-11 Installing a skylight magnetic lock Step 2 Secure the lock magnet to the magnet fixing base using one M4x10 countersunk screw.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles 5.3.1 Installing a Lower Mounting Kit for the End Door Context The lower mounting kit for the end door is required only when 2000 mm high cabinets are placed at an end of the aisle containment, and can be obtained from the end door fitting bag.
Page 108
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-13 Assembling the front and rear sealing plates Step 2 Secure the front and rear sealing plates to the cabinet using four M5x10 tapping screws, as shown by (1) in Figure 5-14.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles 5.3.2 Installing a Revolving Door Procedure Step 1 Assemble the door frame. Place the door posts and upper frame mounting kit on the floor, pull the post side plates from the ends of the door posts, and remove the side plates, as shown by (1) and (2) in Figure 5-15.
Page 110
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-16 Installing a door frame Tighten all screws on the door frame. Step 3 Secure the door panels.
Page 111
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-17 Removing rubber strips from door panels Secure the door panels to the door posts using three M6 countersunk hex socket screws for each hinge, as shown in Figure 5-18.
Page 112
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-18 Installing door panels Secure each hinge on the side of the door post using two M4 screw assemblies, as shown in Figure 5-19.
Page 113
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Step 4 Adjust the gap between door panels. After the door panels are installed and closed, the gap between panels may be uneven and look ungraceful, as described in Table 5-2.
Page 114
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-20 Door panels tilting at both sides Figure 5-21 shows a door with a varying gap between the door panel and upper frame mounting kit (a corner tilts downwards).
Page 115
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles If the door gap is still uneven after the preceding measures are taken, remove and reinstall the rubber strip on one door panel. Adjust the rubber strip positions during installation to verify that the door panel edges are in close contact.
Page 116
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-23 Installing the door box Step 6 Secure the door box. If the door box is evenly and properly placed as shown in Figure 5-24, secure it using M5 screws as shown by (2) in Figure 5-22.
Page 117
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Fault Type Possible Cause Measure Door box tilted with a The top front and rear of the For details about the...
Page 118
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-27 shows a tilted door box. Turn the M6 door box screw in the leveling corner piece nearest to the door frame clockwise to lift the door box until the Λ-shaped gap disappears, as shown by (1) in Figure 5-28.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles If the door box rubs against the fixing screws in the top panel of the cabinet, remove the screws in the top panel, and secure the top panel and the door box to the cabinet using the screws.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-30 Position for attaching a label Ensure that labels are properly aligned. ----End 5.5 (Optional) Installing Aisle Lights Context Install aisle lights in parallel.
Page 121
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-31 Layout of aisle lights (1) Light tube A light tube is 872 mm long. Determine the distance (W) between a light tube and a side of the aisle based on the actual length of the contained aisle in the module: W = (L –...
Page 122
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 5 Installing the Contained Aisles Figure 5-32 Interconnecting light tubes Procedure Step 1 Secure light holders to the skylight plate using M3 screws. Ensure that each light tube is secured by three holders.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 6 (Optional) Installing Cable Troughs (Optional) Installing Cable Troughs 6.1 Installing a 600 mm Wide Cable Trough Context Install two 600 mm cable troughs on the top of every 600 mm wide cabinet. Install two cable troughs on the top of PDCs first, and then install cable troughs on the top of other cabinets along the aisle in sequence.
Page 125
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 6 (Optional) Installing Cable Troughs The trough for routing strong-current cables must be close to the contained aisle. Figure 6-2 PDU2000 cable routing on the top of a cabinet...
Page 126
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 6 (Optional) Installing Cable Troughs Figure 6-4 Rotating the vertical plate by 90 degrees Step 3 Install the other vertical plate into the mounting hole in the second row counting from the front door to the rear door in the same way.
Page 127
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 6 (Optional) Installing Cable Troughs Figure 6-6 Installing a supporting plate Step 5 Install a partition plate. Press both sides of the V-shaped partition plate with hands to decrease the angle to a proper degree, and clamp the clasps at the bottom into the nearby holes.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 6 (Optional) Installing Cable Troughs Figure 6-8 Installing an interconnecting wrench (1) Interconnecting wrench Step 8 Install the cable trough above the rear door in a similar way.
Page 129
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 6 (Optional) Installing Cable Troughs Figure 6-9 300 mm wide cable trough (1) Partition plate (2) Vertical plate (3) Tray Procedure Step 1 Place two vertical plates upright on the top of the 300 mm wide cabinet, and press a tray along the two vertical plates down to the clasps at the bottom.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 6 (Optional) Installing Cable Troughs 6.3 Installing an 800 mm Wide Cable Trough An 800 mm wide cable trough (BOM number: 21501140) is installed on the top of an 800 mm wide cabinet.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Installing Monitoring Devices 7.1 Device Layout in the Network Cabinet There are multiple types of monitoring components. Make installation plans based on the configurations.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-2 Connecting a device ground cable 7.2 (Optional) Installing a Server Context The following installation procedure uses an RH2288 V2 server as an example. For more information, see the documents delivered with the server.
Page 134
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-3 Installing guide rails Place the guide rails horizontally at the installation position in the cabinet. Fix the guide rails using rubber plugs.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices The server uses dual power supplies. Connect the two power cables to different PDU2000s. Figure 7-5 Connecting power cables for the server ----End 7.3 (Optional) Installing a VCN500...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-6 Placing the VCN500 Step 3 Tighten the captive screws in the ears using a Phillips screwdriver, and close the mounting ear buttons.
Page 137
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Step 2 Install the mounting ears delivered with the LAN switch and secure the LAN switch to the rack rails in the front of the cabinet.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices 7.5 Installing an ECC800 Procedure Step 1 Determine the mounting holes for an ECC800 based on the network cabinet device layout, adjust the guide rails, and install floating nuts.
Page 139
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-12 Installing a SIM card Reinstall the ECC800 main control module in the ECC800 subrack, and tighten the captive screws on both sides of the module.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-14 Connecting an antenna cable Figure 7-15 Antenna cable route inside a cabinet Step 6 Connect the ECC800 power cable to the PDU2000.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices If a ground copper bar is installed on the top of the rack rail, install a rack environment unit at the 40 U position. A cable manager should be installed between the rack environment unit and the ground bar.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-17 Control skylight (1) Camera mounting (2) Mounting hole for the multi-functional sensor or smoke hole detector After monitoring components are installed on the control skylight plate and cables are routed, attach ...
Page 143
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-18 Removing front and inner covers Gently insert the micro SD card into the SD card slot. Figure 7-19 Installing an SD card Step 2 Align the holes in the camera base with those in the control skylight, and secure the camera to the control skylight using three M3 screws.
Page 144
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-20 Installing the camera base This camera model provides triple-axis adjustment design. Connect the auxiliary video cable delivered with the camera to a display device such as the monitor. Rotate the camera 0–355 degrees horizontally, 0–75 degrees vertically, or 0–355 degrees in the revolving direction to achieve an appropriate angle.
Page 145
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-22 Installing the inner cover Step 4 Install the front cover of the camera in the direction shown in Figure 7-23, and tighten the screws on the front cover.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices 7.7.2 (Optional) Installing a Smoke Detector Context The screws for installing a smoke detector are located in the fitting bag of the supporting object.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices 7.8 (Optional) Installing Monitoring Components on the End Door 7.8.1 Monitoring Component Layout for the Revolving Door Figure 7-26 Installation positions for monitoring components on the revolving door...
Page 149
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Table 7-1 Names and BOM numbers of monitoring actuators and converters Name Description Number AC actuator 52271876 Install it at the upper frame mounting kit for the PDC in the smart module.
Page 150
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-28 Installing the WiFi converter onto the guide rail (1) Guide rail Step 3 Install stop blocks. Install two stop blocks on the two sides of the WiFi converter to stop the movement of the converter.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-30 Installing WiFi antennas ----End Follow-up Procedure After connecting actuator or converter cables, reinstall the rear plate for the upper frame mounting kit.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices The alarm beacon must be installed on the visible side close to the equipment room door. Procedure Step 1 Remove the buckle from the alarm beacon mounting position.
Page 153
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices After a magnetic lock is installed, the cover can be discarded. Remove the cover at the rear of the mounting kit above the door, remove the four screws at the bottom of the mounting kit, and keep the screws aside.
Page 154
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-34 Removing the fixing plate of a magnetic lock Step 3 Install the magnetic lock fixing plate. Secure the magnetic lock fixing plate to the upper frame mounting kit using eight M4 countersunk screws, as shown by (1) in Figure 7-35.
Page 155
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-36 Installing the mounting plate of the magnetic lock cover Step 6 Install the magnet. Take out the magnet from the magnetic lock fitting bag, and knock the positioning pins of the magnetic into the magnet using a rubber mallet.
Page 156
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-38 Installing the magnet (1) White rubber washer Step 7 (Optional) Adjust the magnet. If the magnet does not work properly after power-on, check that: The magnet provides magnetic force by attaching magnetizable iron parts to it.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-39 Adjusting the gap ----End 7.8.5 Installing Buttons Context The light button and exit button (green) provide the automatic reset function. The BOM number is 16050101.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Step 4 Route the button cable out of the cable hole in the upper part of the post and then into the upper frame mounting kit of the end door.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Name Description Pad power connector Used for securing the pad power connector. holder M5x10 tapping screw Used for securing the pad mounting kit.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-42 Installing a fingerprint and card reader Step 2 Secure the baffle plate with the cable hole in the lower part to the pad mounting kit using the M4 nuts, spring washers, and flat washers, as shown by (2) in Figure 7-42.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-43 Installing a fingerprint and card reader with a keypad Step 2 Secure the baffle plate with the cable hole in the lower part to the pad mounting kit using the M4 nuts, spring washers, and flat washers, as shown by (2) in Figure 7-43.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-44 Installing a card reader with a keypad Step 2 Secure the baffle plate with the cable hole in the middle to the pad mounting kit using the M4 nuts, spring washers, and flat washers, as shown by (2) in Figure 7-44.
Page 163
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-45 Installing an IC card reader Step 2 Secure the baffle plate with the cable hole in the middle to the pad mounting kit using the M4 nuts, spring washers, and flat washers, as shown by (2) in Figure 7-45.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices 7.8.6.5 Installing a Pad Power Connector Prerequisites Before installing a pad power connector, prepare the materials listed in Table 7-3.
Page 165
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-46 Assembling a pad power connector holder (BOM number: 14190892) Figure 7-47 Assembling a pad power connector holder (BOM number: 14190242) Step 2 Connect cables from the power connector to the AC actuator, and route the cables.
Page 166
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-48 Connecting power connector cables (BOM number: 14190892) Figure 7-49 Connecting power connector cables (BOM number: 14190242) Step 3 Secure the pad power connector holder.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices ----End 7.8.6.6 Installing a Pad Context The BOM number of a pad is 01091655. The BOM number of the pad mounting bracket is 21203286.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-52 Installing a pad ----End 7.8.6.7 Securing the Pad Mounting Kit Procedure Step 1 Lay out the cables of monitoring components on the pad mounting kit.
Page 169
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-53 Securing the pad mounting kit Step 4 Insert the pad power adapter into the power connector. Bind the access monitoring cable to the bottom of the power connector holder.
Page 170
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices If no pad is configured, skip this step and route the access monitoring cable from the cable hole in the door box baffle plate.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices ----End 7.9 Installing Monitoring Components on Cable Troughs 7.9.1 Installing a Smart ETH Gateway Prerequisites You have prepared a smart ETH gateway and installation accessories such as the guide rail (delivered with the smart ETH gateway) and screws.
Page 172
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Scenario Rules for Deploying Smart ETH Gateways No rack environment unit deployed Deploy two smart ETH gateways for each end cabinet and IT cabinet in the middle in ...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Procedure Step 1 Use two M4x10 screw assemblies to secure the guide rail for the smart ETH gateway to the planned position, as shown in Figure 7-60.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Procedure Step 1 Attach the ETH converter to the outer side of the side plate of the signal cable trough on the top of the air conditioner.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices When installing temperature sensors on the front door, route the sensors through the sponge strips between the rack rail and side plate, and then secure the sensors.
Page 176
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Procedure Step 1 Mark management areas based on the air conditioner layout. Scenario 1: There is an odd number of IT cabinets between air conditioners. In this scenario, categorize the cabinet in the middle of the two air conditioners to the area of the air conditioner on the left (front view), as shown in Figure 7-63.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-65 Assigning T/H sensors for an odd number of cabinets between air conditioners Figure 7-66 Assigning T/H sensors for an even number of cabinets between air conditioners ----End 7.12 Installing a T/H Sensor...
Page 178
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Context If the air conditioner implements cold-aisle control, install the T/H sensor on the door frame of the IT cabinet front door. If the air conditioner implements hot-aisle control, install the T/H sensor on the door frame of the IT cabinet rear door.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices 7.13 Installing a WLDS900 Water Sensor (Used in Intelligent Micro-Modular) The water sensor mentioned in this section is configured for the smart module, rather than air conditioners.
Page 180
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Procedure Step 1 Connect the water detection cable and conversion cable. Figure 7-69 Connecting cables (1) Conversion cable end B, connected to...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices 7.13.2 Laying Out the Water Detection Cable (Top Pipe Routing) Context Figure 7-71 Laying out a water detection cable (top pipe routing)
Page 182
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-72 Installing a fastener When securing the water detection cable to the concrete floor, use the cable nail clips delivered with the cable to secure the cable.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices 7.13.3 Laying Out the Water Detection Cable (Bottom Pipe Routing) Context Figure 7-75 Laying out a water detection cable (bottom pipe routing)
Page 184
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 7 Installing Monitoring Devices Figure 7-76 Installing a fastener When securing the water detection cable to the concrete floor, use the cable nail clips delivered with the cable to secure the cable.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 9 Installing Cabinet Sealing Plates Installing Cabinet Sealing Plates Context Cabinet sealing plates are used to seal the space under cabinets to ensure that an aisle is airtight.
Page 187
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 9 Installing Cabinet Sealing Plates Figure 9-1 Installing a cabinet sealing plate Step 2 Install another sealing plate for the cabinet rear door in the same way.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Cable Routing 10.1 System Cabling Rules Attaching Cable Labels A cable label must be consistent with the corresponding IT cabinet number.
Page 189
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-1 Neatly organizing cables Keep a large number of cables neat and appealing in a network cabling cabinet by using cable organizers.
Page 190
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-3 Binding cables in different colors Cable Spacing Requirements Comply with the following requirements if possible to lay out different types of cables: Separate AC and DC power cables from diverse non-shielded signal cables.
Page 191
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing If a number of wire terminals are connected to a multi-point connector, provide slack and arrange them neatly to prevent stress on certain wires, as shown in Figure 10-5.
Page 192
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-6 Cutting off the excess part of a cable tie Do not use cable ties at a place where the cables are bent. Otherwise, the cable cores may break due to strong stress, as shown in Figure 10-7.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-8 Direction for securing cable ties 10.2 Cable Routes for the Single-Row Aisle Containment Scenario Figure 10-9 shows how power cables and signal cables are routed in the single-row aisle containment.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-9 Routing power cables and signal cables in the single-row aisle containment scenario (1) Power cable (2) Signal cable (3) Optical fiber...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-10 Cabling route for an electronic lock (A) To the COM1/12V or COM2/12V port on the rack environment unit Figure 10-11 Cabling route for a door status sensor (A) To the AI/DI1 or AI/DI2 port on the rack environment unit 10.4 Cable Routes for the Network Cabinet...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-12 Cable routes for the network cabinet (1) Power cable (2) Signal cable 10.5 Cable Routes for Revolving Door Monitoring Components Figure 10-13 shows the cable routes for revolving door monitoring components.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-13 Cable routes for monitoring components (1) Alarm (2) Pad (3) Access control device (4) Light button beacon (5) Exit button...
Page 198
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-14 Cable routes for the aisle lighting system (1) AC actuator (2) Light (3) Light button After aisle lights are installed, connect cables by performing the following steps: ...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Connect lights in series, and connect the light near the AC actuator to the connector of the cable delivered with the light (the female connector is used as an example), as shown by (1) in Figure 10-16.
Page 200
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-17 shows the ports on the SMS modem. Figure 10-17 Ports on the SMS modem (1) Connecting to the SIM card...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Table 10-2 Relationships between the status of the indicator and the SMS modem Indicator Modem The SMS modem is activated and is not registered with the network.
Page 202
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-18 M-shaped grounding S-shaped Grounding (Not Recommended) If this solution is used, it should be customized. Figure 10-19 shows the cabinet ground points. Connect cabinet ground cables as follows: ...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-19 Cabinet ground points (1) Cabinet branch ground bar (2) Cabinet main ground bar Figure 10-20 S-shaped grounding 10.8.2 (Optional) Connecting Base Ground Cables Figure 10-21 shows the base ground points.
Page 204
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-21 Base ground points (1) Base ground points Connect one end of the base ground cable to any of the base ground points shown by (1) in Figure 10-21, and connect the other end to the general ground copper bar of the equipment room.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing 10.9 Cable Installation for the Power Supply and Distribution System 10.9.1 Connecting Battery Cables Precautions for Connecting Battery Cables For details about how to connect battery cables, see the battery cable connection diagram delivered with the cables.
Page 206
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-24 Attaching the battery label Route and secure cables between layers along the rack rail in the vertical direction, as shown by (1) in Figure 10-25.
Page 207
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-26 Directly connecting two batteries When the length of a battery cable is longer than the distance between two battery terminals, connect the cable in the way shown in Figure 10-27.
Page 208
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-28 Incorrect battery cable connection method Connecting Cables to the Circuit Breaker in a Battery Cabinet Before connecting cables, ensure that the circuit breaker is OFF.
Page 209
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Figure 10-29 Connecting power cables to the circuit breaker (Optional) If the intelligent battery monitoring system is not deployed, use a 04080376 cable to connect the J1 port on the battery control board (BIB) to the corresponding port on the UPS.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Installing Panels Reinstall the circuit breaker panel. Secure filler panels to the rack rails on the rear door, as shown in Figure 10-31.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 10 Cable Routing Device Name Reference Precision PDC PDU8000 Modular Precision PDC Quick Guide (1100 mm Deep) Click Download. 10.10 Connecting Cables for the Cooling System To connect cables to cooling devices, see the documents delivered with the devices.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 12 Power-On Commissioning Power-On Commissioning 12.1 Power-On Sequence Figure 12-1 Power-on sequence 12.2 Commissioning the Power Supply and Distribution System For details about how to commission a certain component of the power supply and distribution system, see the manual delivered with the component.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 12 Power-On Commissioning Device Name References Precision PDC PDU8000 Modular Precision PDC Quick Guide (1100 mm Deep) 12.3 Commissioning the Cooling System If the smart module is located in a humid environment and condensation appears on the outside of the doors of the cold aisle containment, adjust the temperature at the air exhaust vent of the air conditioner or dehumidify the room.
Page 215
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) 12 Power-On Commissioning Document Obtaining Method ECC800 Data Center Controller (ECC The ECC800 version depends on the Version) User Manual version in use. Click on the ECC800 WebUI to obtain the ECC800 version.
Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Appendix A.1 Contacting Huawei Technical Support When contacting Huawei technical support, you need to provide the following information: Full name of the site Name and phone number of the contact person ...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Put aside the removed expansion bolt for securing the cabinet. Figure A-1 Expansion bolt (1) M12 bolt (2) Spring washer (3) Flat washer...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-3 Installing a floating nut A.4 Scenario with a Column (600 mm Wide IT Cabinets Scenario) A.4.1 Scenario Description This section describes the column position in the scenario with a column relative to the adjustable skylight, sealing plates, and cable trays.
Page 219
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix skylight skylight concave sides facing rightwards (7) Column in the equipment room If a column in the data center is irregular, ensure that the maximum cross section of the column does not interfere with cabinets.
Page 220
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-6 Column occupying part of a cabinet place (A < 800 mm and B ≥ 400 mm) Cabinet places on the column side are left blank and sealed by sealing plates. Directions of the concave sides of the sealing plates are shown in Figure A-6.
Page 221
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-7 Column occupying part of a cabinet place (A ≥ 800 mm and B ≥ 400 mm) Cabinet places on the column side are left blank and sealed by sealing plates. Directions of the ...
Page 222
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-8 Column in a row of cabinets (A < 70 mm and B ≥ 400 mm) Cabinet places on the column side are left blank and sealed by sealing plates. Directions of the concave sides of the sealing plates are shown in Figure A-8.
Page 223
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-9 Column in a row of cabinets (A ≥ 70 mm) Seal both sides of the column using sealing plates. Directions of the concave sides of the sealing plates are shown in Figure A-9.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix A.4.2 Installation Process for Scenarios with Columns Figure A-10 Installation flowchart A.4.3 Installing a Cabinet Bottom Sealing Plate Context The cabinet bottom sealing plate installed in the scenario with a column is the same as the mounting kit installed under the end cabinet.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-11 Installation position of the cabinet bottom sealing plate (1) Column (2) Cabinet bottom sealing plate Procedure Step 1 Install the cabinet bottom sealing plate by following the instructions in 5.3.1 Installing a Lower Mounting Kit for the End Door.
Page 226
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Sealing Plate BOM Number 600 mm wide, 2000 mm high sealing plate 21500718 800 mm wide, 2000 mm high sealing plate 21500720...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-12 Installing sealing plates near the aisle (1) Column ----End A.4.5 Installing the Adjustable Skylight An adjustable skylight comprises the following components.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix (7) Telescopic edges A.4.5.1 Installing the Skylight Connective Plate Prerequisites The sealing plates near the aisle have been installed and secured. Procedure Step 1 Secure skylight connective plates to sealing plates or cabinets using eight M8 bolts.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix A.4.5.2 Installing Telescopic Edges Procedure Step 1 Extend the two telescopic edges to an appropriate length and secure them using two M6 bolts.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix ----End A.4.5.3 Installing an Adjustable Skylight Side Sealing Plate Prerequisites A cut tool is prepared. This section uses a hook knife as an example.
Page 231
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Procedure Step 1 Trim the PC plate to an appropriate size using a hook knife. To ensure a neat section after trimming, trim the PC plate using the aisle check tool in the No. 0 packing box.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-21 Securing an adjustable skylight side sealing plate ----End A.4.5.4 Installing the PC Plate Support and PC Plate Procedure Step 1 Select positions for installing PC plate supports. As shown in Figure A-22, PC plate support 1 should be installed closely to the column, and PC plate support 2 should be installed in the middle between PC plate support 1 and the edge of the adjustable skylight.
Page 233
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-22 Adjustable skylight top view (1) Column (2) PC plate support 1 (3) PC plate support 2 Step 2 Secure the two PC plate supports to the telescopic edges of the adjustable skylight using four M6 screws and nuts.
Page 234
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Trim the PC plate using a hook knife and place it on the adjustable skylight. To ensure a neat section after trimming, trim the PC plate using the aisle check tool in the No. 0 packing box.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-25 Installing PC plates (1) PC plate ----End A.4.6 Installing Cable Trays Prerequisites Determine the position and mode (combined or layered) for installing cable trays based on the actual installation environment.
Page 237
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-27 Layered installation Layered installation is used as an example to illustrate the installation method. Procedure Step 1 Use screws to secure the cable tray supports at the coated positions on the cable trays.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Step 2 Secure cable trays to cabinets. Figure A-29 Securing a cable tray ----End A.4.7 Installing Sealing Plates Away from the Aisle Prerequisites The adjustable skylight and cable tray have been installed.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Step 3 Secure the parallel plate obtained from the sealing plate fitting bag to the sealing plate using M4 screws, and then secure the sealing plate to the cabinet.
Page 240
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Context It is recommended that you install the dehumidifiers at the bottom of IT cabinets near air conditioners in the aisle containment. One dehumidifier is required for each module when the load is light but humidity is high.
Page 241
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-32 Installing the tray Step 3 Place the dehumidifier on the tray and move it to its installation position, and secure the dehumidifier mounting ears to the rack rail using a floating nut mounting bar and three floating nuts for each mounting ear.
Page 242
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix When installing the dehumidifier, verify that the air intake vent faces the cold aisle (as shown by A in Figure A-31), and the air exhaust vent faces the hot aisle (as shown by B in Figure A-31).
Page 243
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-35 Connecting the dehumidifier drainpipe (1) Air conditioner drainpipe in the (2) Three-way (3) PVC pipe equipment room valve (4) Female adapter...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Mix AB glue and apply it evenly where the dehumidifier drainpipe and the plug with outer screw threads are connected, and keep the glued parts steady for 30 minutes to solidify the glue.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-37 Connecting cables to the industrial connector (five-core cable) A.7 (Optional) Connecting PDU2000 Cables Context If the PDU2000 is not provided with industrial connectors, connect the PDU2000 cables and lay out the cables on the cabinet top.
Page 247
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-40 Connecting PDU2000 cables (method 3) Figure A-41 Connecting PDU2000 cables (method 4) Step 2 (Optional) Route cables for the half-sized PDU2000, as shown in Figure A-42.
Page 248
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-42 Routing half-sized PDU2000 cables Step 3 Remove the rodent-proof mesh from the top of the cabinet, use diagonal pliers to cut openings that allow cables to run through, and take out the PDU2000 cables through the openings, as shown by (1), (2), and (3) in Figure A-43.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix The number of cables and holes shown in the figure is for reference only. Step 4 Lay out the PDU2000 cables on the top of the cabinet and reinstall the rodent-proof mesh, as shown by (4) in Figure A-43.
Page 250
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix The small cable ring is optional and used to manage the cable routes in the vertical direction. The cable manager is installed in the front of a cabinet by default. You can install it in the rear of a ...
Page 251
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-46 Cable route along a depth-directed cable tray (1) Cable tray (2) Depth-directed cable tray (3) Big cable ring (4) Customer equipment ...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix A.9 Preparing a Monitoring Cable Prerequisites A network cable, cord end terminals, and RJ45 connectors are prepared. The following tools are prepared: −...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-50 Preparing an RS485 monitoring cable for the ECC collector Preparing a Dry Contact Monitoring Cable The method for preparing a dry contact monitoring cable is similar to the method for preparing an RS485 monitoring cable.
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) A Appendix Figure A-51 Connecting fire alarm signal cables to the access actuator A.11 (Optional) Connecting Linkage Cables Between the Equipment Room Fire Extinguishing System and Skylight...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) C Installation Verification Installation Verification Cabinet Installation Checklist Check That Check Result □ Compliant □ The cabinets are placed according to the equipment room layout diagram.
Page 260
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) C Installation Verification Check Item Check Result □ Compliant □ The end doors can be opened and closed smoothly. Incompliant □ Compliant □ The gap between end doors is even.
Page 261
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) C Installation Verification Check Item Check Result □ Compliant □ There is no unnecessary adhesive tape or cable tie on cables. Incompliant Electric Installation Checklist...
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) D Acronyms and Abbreviations Acronyms and Abbreviations Alternating Current Automatic Transfer Switch Battery Circuit Breaker Battery Control I/O Board Battery Interface Module BSPP British Standard Pipe Parallel Thread...
Page 263
FusionModule2000 Smart Modular Data Center Installation Guide (2000 mm High Cabinets, Single-Row Aisle Containment, 380 V) D Acronyms and Abbreviations Fast Ethernet iBAT ibattery Integrated Circuit Internet Technology Negative Temperature Coefficient Power Distribution Cabinet Power Distribution Unit Protective Earthing Power over Ethernet...