Commissioning (software)
10.1
Note before commissioning
Delivery condition
SIMOTION P320‑4 is delivered with:
● Windows operating system
● SIMOTION P Runtime application
NOTICE
Risk of damage to the SIMOTION P320-4
If condensation has developed, wait at least 12 hours before commissioning the device.
10.2
Basic commissioning - initial startup
Requirement
The following requirements must be met before initial commissioning:
● The device is connected to the 24 VDC power supply.
● Equipotential bonding is connected.
10.3
Commissioning requirements
Prior activities
You have already performed the following actions:
● Your system has been installed and wired.
● The installation and parameterization has been completed.
● When networking via PROFINET, the PROFINET addresses of the bus nodes with which
the SIMOTION P320-4 communicates are set.
SIMOTION P320-4 E / P320-4 S
Commissioning and Hardware Installation Manual, 11/2016
10
153